Correspondence & Document Management System (DMS) Subtask Last item under this branch 2026-12-24 95% Correspondence & Document Management System (DMS) Planned: 2025-01-19 → 2026-09-30 Forecast: 2025-01-19 → 2026-12-24 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-06-27 100% Management & governance Planned: 2025-01-19 → 2025-06-07 Actual: 2025-01-19 → 2025-06-27
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-04-27 100% Project plan & baseline Planned: 2025-01-19 → 2025-04-14 Actual: 2025-01-19 → 2025-04-27
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-06-27 100% Monitoring & reporting Planned: 2025-03-13 → 2025-06-07 Actual: 2025-03-21 → 2025-06-27
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-06-27 100% Project plan approved Planned: 2025-06-07 → 2025-06-07 Actual: 2025-06-27 → 2025-06-27 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-10-27 100% Analysis & design Planned: 2025-05-06 → 2025-09-21 Actual: 2025-05-21 → 2025-10-27
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-27 100% Business requirements Planned: 2025-05-06 → 2025-07-30 Actual: 2025-05-21 → 2025-08-27
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-10-27 100% Solution design Planned: 2025-06-28 → 2025-09-21 Actual: 2025-07-21 → 2025-10-27
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-10-27 100% Designs approved Planned: 2025-09-21 → 2025-09-21 Actual: 2025-10-27 → 2025-10-27 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-04-28 100% Build Planned: 2025-08-20 → 2026-03-01 Actual: 2025-09-20 → 2026-04-28
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-27 100% Release 1 Planned: 2025-08-20 → 2025-11-14 Actual: 2025-09-20 → 2025-12-27
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-26 100% Release 2 Planned: 2025-10-13 → 2026-01-06 Actual: 2025-11-20 → 2026-02-26
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-28 100% Integrations Planned: 2025-12-05 → 2026-03-01 Actual: 2026-01-20 → 2026-04-28
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-28 100% Build complete Planned: 2026-03-01 → 2026-03-01 Actual: 2026-04-28 → 2026-04-28 Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-08-28 100% Testing & acceptance Planned: 2026-01-28 → 2026-06-15 Actual: 2026-03-22 → 2026-08-28
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-28 100% System testing Planned: 2026-01-28 → 2026-04-23 Actual: 2026-03-22 → 2026-06-28
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-28 100% User acceptance testing Planned: 2026-03-22 → 2026-06-15 Actual: 2026-05-22 → 2026-08-28
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-28 100% Testing & acceptance complete Planned: 2026-06-15 → 2026-06-15 Actual: 2026-08-28 → 2026-08-28 Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-24 67% Launch & handover Planned: 2026-05-14 → 2026-09-30 Forecast: 2026-07-07 → 2026-12-24 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Training & change Planned: 2026-05-14 → 2026-08-08 Actual: 2026-07-22 → 2026-10-26
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-24 33% Go-live & handover Planned: 2026-07-07 → 2026-09-30 Forecast: 2026-07-07 → 2026-12-24 Float: 0d Drag to change its duration +85
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-24 0% Final handover Planned: 2026-09-30 → 2026-09-30 Forecast: 2026-12-24 → 2026-12-24 Float: 0d Drag to change its dates Final handover