Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+85⁩ days vs approved

Baseline (original = approved)⁦2026-09-30⁩
Current forecast⁦2026-12-24⁩
By earned schedule⁦2027-02-07⁩
Critical activities
2
of ⁦2⁩ open activities
Late activities
1
past their baseline finish
Schedule performance
0.95
earned ÷ planned value
Next milestone
in 57 days
Final handover
Expand allCollapse all
Activity
Correspondence & Document Management System (DMS)Planned: ⁦2025-01-19⁩ → ⁦2026-09-30⁩Forecast: ⁦2025-01-19⁩ → ⁦2026-12-24⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-01-19⁩ → ⁦2025-06-07⁩Actual: ⁦2025-01-19⁩ → ⁦2025-06-27⁩
Project plan & baselinePlanned: ⁦2025-01-19⁩ → ⁦2025-04-14⁩Actual: ⁦2025-01-19⁩ → ⁦2025-04-27⁩
Monitoring & reportingPlanned: ⁦2025-03-13⁩ → ⁦2025-06-07⁩Actual: ⁦2025-03-21⁩ → ⁦2025-06-27⁩
Project plan approvedPlanned: ⁦2025-06-07⁩ → ⁦2025-06-07⁩Actual: ⁦2025-06-27⁩ → ⁦2025-06-27⁩Project plan approved
Analysis & designPlanned: ⁦2025-05-06⁩ → ⁦2025-09-21⁩Actual: ⁦2025-05-21⁩ → ⁦2025-10-27⁩
Business requirementsPlanned: ⁦2025-05-06⁩ → ⁦2025-07-30⁩Actual: ⁦2025-05-21⁩ → ⁦2025-08-27⁩
Solution designPlanned: ⁦2025-06-28⁩ → ⁦2025-09-21⁩Actual: ⁦2025-07-21⁩ → ⁦2025-10-27⁩
Designs approvedPlanned: ⁦2025-09-21⁩ → ⁦2025-09-21⁩Actual: ⁦2025-10-27⁩ → ⁦2025-10-27⁩Designs approved
BuildPlanned: ⁦2025-08-20⁩ → ⁦2026-03-01⁩Actual: ⁦2025-09-20⁩ → ⁦2026-04-28⁩
Release 1Planned: ⁦2025-08-20⁩ → ⁦2025-11-14⁩Actual: ⁦2025-09-20⁩ → ⁦2025-12-27⁩
Release 2Planned: ⁦2025-10-13⁩ → ⁦2026-01-06⁩Actual: ⁦2025-11-20⁩ → ⁦2026-02-26⁩
IntegrationsPlanned: ⁦2025-12-05⁩ → ⁦2026-03-01⁩Actual: ⁦2026-01-20⁩ → ⁦2026-04-28⁩
Build completePlanned: ⁦2026-03-01⁩ → ⁦2026-03-01⁩Actual: ⁦2026-04-28⁩ → ⁦2026-04-28⁩Build complete
Testing & acceptancePlanned: ⁦2026-01-28⁩ → ⁦2026-06-15⁩Actual: ⁦2026-03-22⁩ → ⁦2026-08-28⁩
System testingPlanned: ⁦2026-01-28⁩ → ⁦2026-04-23⁩Actual: ⁦2026-03-22⁩ → ⁦2026-06-28⁩
User acceptance testingPlanned: ⁦2026-03-22⁩ → ⁦2026-06-15⁩Actual: ⁦2026-05-22⁩ → ⁦2026-08-28⁩
Testing & acceptance completePlanned: ⁦2026-06-15⁩ → ⁦2026-06-15⁩Actual: ⁦2026-08-28⁩ → ⁦2026-08-28⁩Testing & acceptance complete
Launch & handoverPlanned: ⁦2026-05-14⁩ → ⁦2026-09-30⁩Forecast: ⁦2026-07-07⁩ → ⁦2026-12-24⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-05-14⁩ → ⁦2026-08-08⁩Actual: ⁦2026-07-22⁩ → ⁦2026-10-26⁩
Go-live & handoverPlanned: ⁦2026-07-07⁩ → ⁦2026-09-30⁩Forecast: ⁦2026-07-07⁩ → ⁦2026-12-24⁩Float: ⁦0⁩dDrag to change its duration+85
Final handoverPlanned: ⁦2026-09-30⁩ → ⁦2026-09-30⁩Forecast: ⁦2026-12-24⁩ → ⁦2026-12-24⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦2⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦1⁩ activity with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Go-live & handover” needs a pace ⁦4.0⁩× faster than it has kept

It earned ⁦33%⁩ in 113 days; the forecast assumes the rest in 57 days. At the pace so far it finishes on ⁦2027-06-14⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 55 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

20
36
58
74
85
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close