Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
SCA-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-10-19⁩
Hijri
8 Jumada I 1448 AH
In approvalCR-2026-014Re-route the network in Al-Rawdah district

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-018
Project
Secure Enterprise Network
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1The change

TitleAuto-filled
Re-route the network in Al-Rawdah district
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Omar H. Bawazir
Raised onAuto-filled
⁦2026-10-19⁩

Reason

The municipality objected to digging on Al-Rawdah’s main streets

Justification

The side-street route gets a permit within two weeks

2Impact analysis

Cost

SAR +1.2M

Schedule

+20 days

Risk

12 → 6

Benefits

0%

Risk impact

Resolves the standing objection

Benefits impact

No effect on benefits

3The approval decision

The PMO’s recommendation

Impact analysis in progress at the PMO

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Omar H. BawazirDirector, IT InfrastructureSubmitted—⁦2026-10-19⁩ 14:17
2Project managerTechnical acceptanceApproval engineProject managerPre-breach alert—⁦2026-10-20⁩ 08:00
3Project managerTechnical acceptanceApproval engineEscalated automatically to Programme manager (Eng. Omar H. Bawazir) on ⁦2026-10-21⁩Automatic escalation—⁦2026-10-21⁩ 08:05

Signatures

Project manager

Eng. Omar H. Bawazir

Awaiting decision

PMO review & impact analysis

Ghada A. Al-Shahrani

Later

Financial impact

Munirah A. Al-Khalidi

Later

Contractual impact

Mazen A. Al-Hazmi

Later

Change Committee

Dr. Mohammed I. Al-Subaie

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Omar H. Bawazir on ⁦2026-10-19⁩

  1. Technical acceptance

    Project manager

    Eng. Omar H. Bawazir · Project manager
    6 working days overdueAction time limit exceeded · Limit 1 working dayLimit 1 working day · Due ⁦2026-10-20⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-20⁩

    Escalated automatically to Programme manager (Eng. Omar H. Bawazir) on ⁦2026-10-21⁩

    Waiting on Eng. Omar H. Bawazir
  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 2 working days · Expected by ⁦2026-10-22⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-10-26⁩

  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Limit 2 working days · Expected by ⁦2026-10-28⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 3 working days · Expected by ⁦2026-11-02⁩

Steps that do not apply to this record

  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-19⁩

    The request as raised

    Eng. Omar H. Bawazir

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close