Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-10-13⁩
Hijri
10 Rabiʻ II 1446 AH
ApprovedDMD-2026-018Secure Enterprise Network

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-018
Project
Secure Enterprise Network
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1The proposalAuto-filled

TitleAuto-filled
Secure Enterprise Network
Proposed byAuto-filled
Eng. Omar H. Bawazir
DepartmentAuto-filled
IT Infrastructure Department
Submitted onAuto-filled
⁦2024-10-13⁩
Proposal numberAuto-filled
DMD-2026-018

2Justification

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

3Objectives

  1. Strong technical capabilities
  2. SCA services and programmes in every region

Strategic objectives served

  • SO-4.1 — Strong technical capabilities
  • SO-3.1 — SCA services and programmes in every region

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 132M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 95M
Supervision & consultingSAR 18.5M
Internal teamSAR 11.9M
Contingency reserve (5%)SAR 6.6M
TotalSAR 132M

6Initial risks

RiskLevelProposed response
Higher reinstatement costs after network trenchingMediumTreated in the risk management plan
Municipal objections to trenching in built-up districtsMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Omar H. BawazirDirector, IT InfrastructureSubmitted—⁦2024-10-13⁩ 11:50
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-10-14⁩ 09:30
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-10-16⁩ 10:37
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-10-21⁩ 11:44
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-10-24⁩ 11:26
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2024-10-30⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-10-31⁩ 13:58

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-10-14⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-10-16⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2024-10-21⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-10-24⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-10-31⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Omar H. Bawazir on ⁦2024-10-13⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-10-14⁩ at ⁦09:30⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-10-16⁩ at ⁦10:37⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2024-10-21⁩ at ⁦11:44⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-10-24⁩ at ⁦11:26⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-10-31⁩ at ⁦13:58⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-11-03⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Omar H. Bawazir

  2. V1Returned for edit⁦2024-10-13⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Omar H. Bawazir

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close