Working
Working baseline
- Finish
- 2027-10-31
- Budget
- SAR 33M
- 17 activities
The working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.
Created 2026-10-28 · by Eng. Mishari K. Al-Otaibi
HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.
Budget (BAC)
Actual cost
8% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
No baseline approved yet
The project is in Planning: the working plan is ready (17 activities, finish 2027-10-31, budget SAR 33M). Save it as the first baseline and send it for approval; once approved it is locked and changes only through an approved change request.
Working
The working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.
Created 2026-10-28 · by Eng. Mishari K. Al-Otaibi
What changed from version A to version B
No approved baseline yet — measured against the working plan
Every saved version with its reason and reference