PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V1
Form date
⁦2026-02-26⁩
Hijri
9 Ramadan 1447 AH
In approvalPRJ-2026-026Energy Retrofit of Existing SCA Buildings (ESCO)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Energy Retrofit of Existing SCA Buildings (ESCO)
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-02-01⁩

Baseline finish

⁦2027-06-30⁩

Forecast finish

⁦2027-10-31⁩

SPI

0.89

MilestonePlannedForecastSlip
Project plan approved⁦2026-05-18⁩⁦2026-10-26⁩+161 days
Designs approved⁦2026-08-08⁩⁦2027-01-16⁩+161 days
Build complete⁦2026-12-08⁩⁦2027-05-04⁩+147 days
Testing & acceptance complete⁦2027-04-09⁩⁦2027-08-20⁩+133 days
Final handover⁦2027-06-30⁩⁦2027-10-31⁩+123 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2026-04-07⁩Eng. Mishari K. Al-Otaibi
Monitoring & reporting⁦4%⁩⁦2026-05-18⁩Eng. Bandar M. Al-Shammari
Detailed design⁦6%⁩⁦2026-06-28⁩Eng. Bandar M. Al-Shammari
Permits & approvals⁦6%⁩⁦2026-08-08⁩Sarah A. Al-Qarni
Site works & excavation⁦12%⁩⁦2026-09-17⁩Sarah A. Al-Qarni
Structure⁦12%⁩⁦2026-10-28⁩Eng. Mishari K. Al-Otaibi
Finishes⁦12%⁩⁦2026-12-08⁩Eng. Bandar M. Al-Shammari
Supply⁦10%⁩⁦2027-01-18⁩Eng. Mishari K. Al-Otaibi
Installation⁦10%⁩⁦2027-02-28⁩Eng. Bandar M. Al-Shammari
Testing & commissioning⁦10%⁩⁦2027-04-09⁩Sarah A. Al-Qarni
Provisional acceptance⁦7%⁩⁦2027-05-20⁩Eng. Bandar M. Al-Shammari
Final acceptance⁦7%⁩⁦2027-06-30⁩Sarah A. Al-Qarni
Accepted with a certificate⁦8%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0043Funding left out of the 2027 budget, keeping the tender suspended16EscalateEng. Mishari K. Al-Otaibi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Mishari K. Al-Otaibi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Mishari K. Al-Otaibi
PMOData and indicator updatesWeeklyEng. Mishari K. Al-Otaibi
BeneficiariesWhat changes and whenAt each milestoneEng. Mishari K. Al-Otaibi
Team memberRoleAllocation
Eng. Mishari K. Al-OtaibiProject manager (on hold)⁦15%⁩
Rami Al-KhatibFinancing-model adviser, ESCO contract⁦25%⁩
Mazen A. Al-HazmiESCO tender⁦20%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencySubmitted—⁦2026-10-23⁩ 12:45
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-27⁩ 14:47

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2026-10-27⁩

Technical acceptance — project owner

Eng. Bandar M. Al-Shammari

Awaiting decision

Cash flow & financial commitment

Munirah A. Al-Khalidi

Later

Sponsor approval

Sarah A. Al-Qarni

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V1

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2026-10-23⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-27⁩ at ⁦14:47⁩

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Bandar M. Al-Shammari · Project owner
    2 working days leftWithin the time limit · Limit 3 working daysLimit 3 working days · Due ⁦2026-11-01⁩
    Waiting on Eng. Bandar M. Al-Shammari
  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-11-03⁩

  4. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-08⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V2In approval⁦2026-02-26⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for editCurrent⁦2026-02-12⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Mishari K. Al-Otaibi