Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 33M split into spent, committed and left, with the estimate at completion

EAC SAR 33M
Revised request SAR 33M
  • Actual spendSAR 2.6M
  • Committed, not spentSAR 460K
  • Allotted, uncommittedSAR 28.9M
  • Contingency availableSAR 990K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 31.7M
Original budgetwhen the first baseline was approved
SAR 33M
Approved budgetafter approved change requests
SAR 33M
Current budgetavailable to spend now
SAR 33M
Revised budgetif the pending changes are approved
SAR 33M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 3.1M
Contracts0 active contracts
SAR 0
Purchase orders⁦2⁩ orders
SAR 3.1M
Remaining budgetapproved less actual
SAR 30.4M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 2.6M
Accrualswork done, not yet invoiced
SAR 106K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 33M
ContingencySAR 660K drawn of SAR 1.7M
SAR 990K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 31.7M
ApprovedSAR 33M
Estimate at completionSAR 33M
Approved is SAR 1.3M (⁦4.1%⁩) above the estimate
The estimate at completion is SAR 1.3M (⁦4.1%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-11-18⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-71026
  • WBS elements⁦5⁩ elements · P-2026-026.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 660K drawn of SAR 1.7M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 660K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.921.981.981.98⁦−0.06⁩
2Design & permits3.840.710.663.89⁦−0.05⁩
3Civil works12.160.190.0012.34⁦−0.18⁩
4MEP works9.600.150.009.74⁦−0.14⁩
5Handover4.480.070.004.55⁦−0.07⁩
Unallocated contingency0.990.000.000.50⁦+0.50⁩
Total33.003.102.6433.00⁦+0.00⁩

Budget split

WBS

SAR 33M

Budget

  • Management & governanceSAR 1.9M⁦6%⁩
  • Design & permitsSAR 3.8M⁦12%⁩
  • Civil worksSAR 12.2M⁦37%⁩
  • MEP worksSAR 9.6M⁦29%⁩
  • HandoverSAR 4.5M⁦14%⁩
  • Unallocated contingencySAR 990K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2030-05-22⁩+1,057

SPI(t) ⁦0.33⁩ against the approved finish ⁦2027-06-30⁩

Planned valuePV
SAR 18M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 2.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 2.6M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 33M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−15.31⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.15
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 33M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 30.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 33M
  • If the rest goes to planSAR 33M
  • At cost and schedule performanceSAR 209.1M
  • The PM’s bottom-up estimateSAR 33M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 33M

Variance at completion: ⁦+0.00⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close