PRJ-2026-026On hold3PlanningWaterfall
Energy Retrofit of Existing SCA Buildings (ESCO)
Add to watchlistHVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.
Project managerEng. Mishari K. Al-OtaibiProject sponsorSarah A. Al-QarniProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 33M
Actual cost
SAR 2.6M
8% of budget
Progress
8%Awaiting acceptance 6%
Estimate at completion
SAR 33M
SPI · CPI
0.89Schedule performance index · 0.891.00Cost performance index · 1.00
Forecast finish
2027-10-31
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work32M17 elements
Unallocated contingency990KSAR 1.7M
Budget at completion33MPRJ-2026-026
Weighted progress8%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total8%32.012.64