PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+123⁩ days vs approved

Baseline (original = approved)⁦2027-06-30⁩
Current forecast⁦2027-10-31⁩
By earned schedule⁦2030-05-22⁩
Critical activities
11
of ⁦14⁩ open activities
Late activities
10
past their baseline finish
Schedule performance
0.15
earned ÷ planned value
Next milestone
in 80 days
Designs approved
Expand allCollapse all
Activity
Energy Retrofit of Existing SCA Buildings (ESCO)Planned: ⁦2026-02-01⁩ → ⁦2027-06-30⁩Forecast: ⁦2026-02-01⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-02-01⁩ → ⁦2026-05-18⁩Actual: ⁦2026-02-01⁩ → ⁦2026-10-26⁩
Project plan & baselinePlanned: ⁦2026-02-01⁩ → ⁦2026-04-07⁩Actual: ⁦2026-02-01⁩ → ⁦2026-07-17⁩
Monitoring & reportingPlanned: ⁦2026-03-14⁩ → ⁦2026-05-18⁩Actual: ⁦2026-05-16⁩ → ⁦2026-10-26⁩
Project plan approvedPlanned: ⁦2026-05-18⁩ → ⁦2026-05-18⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Project plan approved
Design & permitsPlanned: ⁦2026-04-24⁩ → ⁦2026-08-08⁩Forecast: ⁦2026-04-24⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Detailed designPlanned: ⁦2026-04-24⁩ → ⁦2026-06-28⁩Forecast: ⁦2026-04-24⁩ → ⁦2026-12-11⁩Float: ⁦0⁩dDrag to change its duration+166
Permits & approvalsPlanned: ⁦2026-06-03⁩ → ⁦2026-08-08⁩Forecast: ⁦2026-11-19⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its dates+161
Designs approvedPlanned: ⁦2026-08-08⁩ → ⁦2026-08-08⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦288⁩dDrag to change its datesDesigns approved
Civil worksPlanned: ⁦2026-07-14⁩ → ⁦2026-12-08⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-05-04⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2026-07-14⁩ → ⁦2026-09-17⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-02-21⁩Float: ⁦0⁩dDrag to change its dates+157
StructurePlanned: ⁦2026-08-24⁩ → ⁦2026-10-28⁩Forecast: ⁦2027-01-30⁩ → ⁦2027-03-29⁩Float: ⁦0⁩dDrag to change its dates+152
FinishesPlanned: ⁦2026-10-04⁩ → ⁦2026-12-08⁩Forecast: ⁦2027-03-07⁩ → ⁦2027-05-04⁩Float: ⁦0⁩dDrag to change its dates+147
Build completePlanned: ⁦2026-12-08⁩ → ⁦2026-12-08⁩Forecast: ⁦2027-05-04⁩ → ⁦2027-05-04⁩Float: ⁦180⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2026-11-14⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-04-12⁩ → ⁦2027-08-20⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-11-14⁩ → ⁦2027-01-18⁩Forecast: ⁦2027-04-12⁩ → ⁦2027-06-09⁩Float: ⁦0⁩dDrag to change its dates+142
InstallationPlanned: ⁦2026-12-24⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-05-18⁩ → ⁦2027-07-15⁩Float: ⁦0⁩dDrag to change its dates+137
Testing & commissioningPlanned: ⁦2027-02-03⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-06-23⁩ → ⁦2027-08-20⁩Float: ⁦0⁩dDrag to change its dates+133
Testing & acceptance completePlanned: ⁦2027-04-09⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-08-20⁩ → ⁦2027-08-20⁩Float: ⁦72⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2027-03-16⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-07-29⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2027-03-16⁩ → ⁦2027-05-20⁩Forecast: ⁦2027-07-29⁩ → ⁦2027-09-25⁩Float: ⁦0⁩dDrag to change its dates+128
Final acceptancePlanned: ⁦2027-04-26⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-09-03⁩ → ⁦2027-10-31⁩Float: ⁦0⁩dDrag to change its dates+123
Final handoverPlanned: ⁦2027-06-30⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-10-31⁩ → ⁦2027-10-31⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦14⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦10⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Detailed design” needs a pace ⁦8.6⁩× faster than it has kept

It earned ⁦33%⁩ in 187 days; the forecast assumes the rest in 44 days. At the pace so far it finishes on ⁦2027-11-12⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 156 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

161
161
147
G1G2G3

The critical chain

In date order, to final acceptance