Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project lifecycle and its gates

Current phase: Planning. Pick a gate on the track to review it.

  1. Gate into «Initiation»DecisionGoDate3 December 2025All criteria and required documents met.Pre-startComplete
  2. Gate into «Planning»DecisionGoDate1 February 2026All criteria and required documents met.InitiationComplete
  3. Gate into «Execution»DecisionNot held yetDate24 April 2026PlanningCurrent stageCurrent stage
  4. Gate into «Closure»DecisionNot held yet4ExecutionNot started
  5. 5ClosureNot started

What each stage requires

The documents and approvals each gate asks for before the next stage.

G3Next gateProjects Steering Committee

Planning gate — plan and baseline approved

3Planning4ExecutionPlanned for ⁦2026-04-24⁩187 days overdue2026-04-247 Dhuʻl-Qiʻdah 1447 AH
63/100

Gate readiness

Enough for a conditional go only

Automated control: no move until the criteria are met

  • ⁦3⁩ mandatory checklist items open
  • ⁦2⁩ required documents not approved
  • ⁦2⁩ mandatory criteria under ⁦70⁩ points
  • Weighted score ⁦63⁩ under the pass mark ⁦75⁩

Checklist

⁦2⁩ of ⁦6⁩ done

  • Project management plan: schedule, deliverables, risks, communication, quality and benefitsMandatory
  • Deliverables defined with weights that sum to ⁦100%⁩Mandatory
  • Schedule and baseline approved and lockedMandatory
  • Approved budget and expected commitmentsMandatory
  • Finance and procurement sign-off where money or a contract is involvedMandatory
  • Initial risk register

Required documents

⁦2⁩ of ⁦4⁩ approved

  • Project management planApproved · V1
  • Approved baselineNot submitted
  • Deliverables register with weightsNot submitted
  • Contract or purchase orderApproved · V1

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Schedule realismweight ⁦30⁩%Not met

    Awaiting evidence from the project team.

  • Cost estimate completenessweight ⁦30⁩%Not met

    Awaiting evidence from the project team.

  • Deliverables and acceptance criteria clearweight ⁦25⁩%Met

    Awaiting evidence from the project team.

  • Quality of the risk planweight ⁦15⁩%

    Awaiting evidence from the project team.

Approvers

Projects Steering Committee

  • Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
  • Sarah A. Al-QarniProject sponsorVote pending
  • Dr. Noura M. Al-OtaibiPMO directorVote pending
  • Munirah A. Al-KhalidiFinance & procurementVote pending

Gate decision

The decision and its rationale go into the gate log and to the team.

What is the decision based on? It stays in the log.0 / 600

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close