PRJ-2026-026On hold3PlanningWaterfall
Energy Retrofit of Existing SCA Buildings (ESCO)
Add to watchlistHVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.
Project managerEng. Mishari K. Al-OtaibiProject sponsorSarah A. Al-QarniProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 33M
Actual cost
SAR 2.6M
8% of budget
Progress
8%Awaiting acceptance 6%
Estimate at completion
SAR 33M
SPI · CPI
0.89Schedule performance index · 0.891.00Cost performance index · 1.00
Forecast finish
2027-10-31
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
No update cards for this project — they start with execution.