PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work32M⁦17⁩ elements
Unallocated contingency990KSAR 1.7M
Budget at completion33MPRJ-2026-026
Weighted progress⁦8%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project637⁦2026-02-01⁩⁦2027-10-31⁩⁦8%⁩32.012.64—
1
Phase267⁦2026-02-01⁩⁦2026-10-26⁩⁦100%⁩1.921.98—
1.1
WBS element166⁦2026-02-01⁩⁦2026-07-17⁩⁦100%⁩0.960.990 / 1
1.2
WBS element163⁦2026-05-16⁩⁦2026-10-26⁩⁦100%⁩0.960.991 / 2
2
Phase267⁦2026-04-24⁩⁦2027-01-16⁩⁦17%⁩3.840.66—
2.1
WBS element231⁦2026-04-24⁩⁦2026-12-11⁩⁦33%⁩1.920.661 / 1
2.2
WBS element58⁦2026-11-19⁩⁦2027-01-16⁩⁦0%⁩1.92—1 / 2
3
Phase130⁦2026-12-25⁩⁦2027-05-04⁩⁦0%⁩12.16——
3.1
WBS element58⁦2026-12-25⁩⁦2027-02-21⁩⁦0%⁩4.05—1 / 1
3.2
WBS element58⁦2027-01-30⁩⁦2027-03-29⁩⁦0%⁩4.05—1 / 1
3.3
WBS element58⁦2027-03-07⁩⁦2027-05-04⁩⁦0%⁩4.05—1 / 2
4
Phase130⁦2027-04-12⁩⁦2027-08-20⁩⁦0%⁩9.60——
4.1
WBS element58⁦2027-04-12⁩⁦2027-06-09⁩⁦0%⁩3.20—1 / 1
4.2
WBS element58⁦2027-05-18⁩⁦2027-07-15⁩⁦0%⁩3.20—1 / 1
4.3
WBS element58⁦2027-06-23⁩⁦2027-08-20⁩⁦0%⁩3.20—1 / 2
5
Phase94⁦2027-07-29⁩⁦2027-10-31⁩⁦0%⁩4.48——
5.1
WBS element58⁦2027-07-29⁩⁦2027-09-25⁩⁦0%⁩2.24—1 / 1
5.2
WBS element58⁦2027-09-03⁩⁦2027-10-31⁩⁦0%⁩2.24—1 / 1
Total⁦8%⁩32.012.64