PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
SCA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
Hijri
5 Rabiʻ II 1448 AH
ApprovedPRJ-2026-026Energy Retrofit of Existing SCA Buildings (ESCO)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Energy Retrofit of Existing SCA Buildings (ESCO)
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1Weight and relative weightAuto-filled

Project weight score

59 of 100

Relative weight in the portfolio

⁦17.4%⁩

Portfolio

Building Rehabilitation & Sustainability Portfolio

5 projects

Its share of the portfolio’s progress

1.0 points of 54.9%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩321.0
Budget sizeApproved budget (BAC)⁦25%⁩210.0
Impact on contractors & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩48.0
Project classificationThe project’s classification⁦10%⁩24.0
Weight score—⁦100%⁩—59

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Al-Khobar Branch — Rehabilitation & Extension83⁦24.4%⁩⁦68%⁩
Solar Power for SCA Buildings & Centres71⁦20.9%⁩⁦58%⁩
Khamis Mushait Training Centre Rehabilitation65⁦19.1%⁩⁦97%⁩
Al-Jouf Training Centre Rehabilitation62⁦18.2%⁩⁦36%⁩
Energy Retrofit of Existing SCA Buildings (ESCO)59⁦17.4%⁩⁦6%⁩
Weighted portfolio progress—⁦100%⁩⁦54.9%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2026-09-16⁩ 10:55
2Weight model complianceMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-09-20⁩ 12:09
3Portfolio manager approvalTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApproved—⁦2026-09-22⁩ 13:16

Signatures

Weight model compliance

Ghada A. Al-Shahrani

Approved⁦2026-09-20⁩

Portfolio manager approval

Eng. Mishari K. Al-Otaibi

Approved⁦2026-09-22⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-20⁩ at ⁦12:09⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2026-09-22⁩ at ⁦13:16⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Noura M. Al-Otaibi

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity