PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Form no.
SCA-PMO-F10
Template edition
1.0
Version
V1
Form date
⁦2026-09-21⁩
Hijri
10 Rabiʻ II 1448 AH
ApprovedSTS-026-1Suspension — Energy Retrofit of Existing SCA Buildings (ESCO)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Energy Retrofit of Existing SCA Buildings (ESCO)
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1The decision asked for

Action
Suspension
Status nowAuto-filled
Active
Status afterAuto-filled
Suspended
Requested onAuto-filled
⁦2026-09-21⁩
Planned resumption
⁦2027-01-15⁩
Length of the suspensionAuto-filled
116 days

2Rationale

Waiting for 2027 funding of the performance contracts with the energy service companies.

3Effect on the projectAuto-filled

Approved budget

SAR 33M

Committed

SAR 3.1M

Actual

SAR 2.6M

Progress

⁦8%⁩

A suspended project keeps its stage and resumes in it; its progress is frozen in the portfolio’s progress while suspended.

Approval logChain: Suspension, resumption & cancellation · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencySubmitted—⁦2026-09-21⁩ 11:38
2PMO opinionMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2026-09-22⁩ 09:06
3Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2026-09-24⁩ 12:00
4Effect on financial commitmentsFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-09-24⁩ 13:28
5Sponsor’s decisionTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2026-09-27⁩ 12:27

Signatures

PMO opinion

Dr. Noura M. Al-Otaibi

Approved⁦2026-09-22⁩

Effect on financial commitments

Munirah A. Al-Khalidi

Approved⁦2026-09-24⁩

Sponsor’s decision

Sarah A. Al-Qarni

Approved⁦2026-09-27⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2026-09-24⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F10 · version V1

Suspension, resumption & cancellation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Suspension, resumption & cancellation · version ⁦1⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2026-09-21⁩

  1. Methodology review

    PMO opinion

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2026-09-22⁩ at ⁦09:06⁩

  2. Financial approval

    Effect on financial commitments

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-09-24⁩ at ⁦13:28⁩

  3. Technical acceptance

    Sponsor’s decision

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2026-09-27⁩ at ⁦12:27⁩

  4. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    On the path because: Suspension longer than the sponsor’s authority?From the authority matrix

    Approved · ⁦2026-09-24⁩ at ⁦12:00⁩

Steps that do not apply to this record

  • Contracts suspended or resumed — the condition «Contract link?» does not hold
  • Secretary-General — the condition «Cancelling a project of SAR 100M or more?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-09-21⁩

    Waiting for 2027 funding of the performance contracts with the energy service companies.

    Eng. Mishari K. Al-Otaibi

Only one version so far.