PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

1Achieved
0On track
3At risk
1Late
Average delay145 days
Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-12-08⁩Forecast / actual: ⁦2027-05-04⁩Delay: 147 daysG3 +147
Executive
Project plan approvedPlanned: ⁦2026-05-18⁩Forecast / actual: ⁦2026-10-26⁩Delay: 161 daysG1 +161
Payment
Final handoverPlanned: ⁦2027-06-30⁩Forecast / actual: ⁦2027-10-31⁩Delay: 123 daysG5 +123
Regulatory
Testing & acceptance completePlanned: ⁦2027-04-09⁩Forecast / actual: ⁦2027-08-20⁩Delay: 133 daysG4 +133
Project
Designs approvedPlanned: ⁦2026-08-08⁩Forecast / actual: ⁦2027-01-16⁩Delay: 161 daysG2 +161

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-05-18⁩⁦2026-10-26⁩⁦+161⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-08-08⁩⁦2027-01-16⁩⁦+161⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saLate0Not requested
Build completeMS-G3Contractual⁦2026-12-08⁩⁦2027-05-04⁩⁦+147⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-04-09⁩⁦2027-08-20⁩⁦+133⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-06-30⁩⁦2027-10-31⁩⁦+123⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦8%⁩

Awaiting acceptance

⁦6%⁩

Not handed in

⁦86%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline026-D1⁦4%⁩CRT-026-01ApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saEng. Bandar M. Al-Shammari⁦2026-04-07⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting026-D2⁦4%⁩CRT-026-02ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2026-05-18⁩V1⁦3⁩ of ⁦3⁩
Detailed design026-D3⁦6%⁩—SubmittedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2026-06-28⁩V1⁦1⁩ of ⁦3⁩
Permits & approvals026-D4⁦6%⁩—DraftSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saEng. Bandar M. Al-Shammari⁦2026-08-08⁩V0⁦0⁩ of ⁦3⁩
Site works & excavation026-D5⁦12%⁩—DraftSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saEng. Bandar M. Al-Shammari⁦2026-09-17⁩V0⁦0⁩ of ⁦3⁩
Structure026-D6⁦12%⁩—DraftEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saEng. Bandar M. Al-Shammari⁦2026-10-28⁩V0⁦0⁩ of ⁦3⁩
Finishes026-D7⁦12%⁩—DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2026-12-08⁩V0⁦0⁩ of ⁦3⁩
Supply026-D8⁦10%⁩—DraftEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saEng. Bandar M. Al-Shammari⁦2027-01-18⁩V0⁦0⁩ of ⁦3⁩
Installation026-D9⁦10%⁩—DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2027-02-28⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning026-D10⁦10%⁩—DraftSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saEng. Bandar M. Al-Shammari⁦2027-04-09⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance026-D11⁦7%⁩—DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2027-05-20⁩V0⁦0⁩ of ⁦3⁩
Final acceptance026-D12⁦7%⁩—DraftSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saEng. Bandar M. Al-Shammari⁦2027-06-30⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩