Energy Retrofit of Existing SCA Buildings (ESCO)
Add to watchlistHVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.
Budget (BAC)
Actual cost
8% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-05-18 | 2026-10-26 | +161 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-08-08 | 2027-01-16 | +161 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | Late | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2026-12-08 | 2027-05-04 | +147 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-04-09 | 2027-08-20 | +133 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-06-30 | 2027-10-31 | +123 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
8%Awaiting acceptance
6%Not handed in
86%Deliverable flow
Display options
| Project plan & baseline026-D1 | 4% | CRT-026-01 | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | Eng. Bandar M. Al-Shammari | 2026-04-07 | V1 | 3 of 3 |
| Monitoring & reporting026-D2 | 4% | CRT-026-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-05-18 | V1 | 3 of 3 |
| Detailed design026-D3 | 6% | — | Submitted | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-06-28 | V1 | 1 of 3 |
| Permits & approvals026-D4 | 6% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Eng. Bandar M. Al-Shammari | 2026-08-08 | V0 | 0 of 3 |
| Site works & excavation026-D5 | 12% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Eng. Bandar M. Al-Shammari | 2026-09-17 | V0 | 0 of 3 |
| Structure026-D6 | 12% | — | Draft | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | Eng. Bandar M. Al-Shammari | 2026-10-28 | V0 | 0 of 3 |
| Finishes026-D7 | 12% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-12-08 | V0 | 0 of 3 |
| Supply026-D8 | 10% | — | Draft | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | Eng. Bandar M. Al-Shammari | 2027-01-18 | V0 | 0 of 3 |
| Installation026-D9 | 10% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2027-02-28 | V0 | 0 of 3 |
| Testing & commissioning026-D10 | 10% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Eng. Bandar M. Al-Shammari | 2027-04-09 | V0 | 0 of 3 |
| Provisional acceptance026-D11 | 7% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2027-05-20 | V0 | 0 of 3 |
| Final acceptance026-D12 | 7% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Eng. Bandar M. Al-Shammari | 2027-06-30 | V0 | 0 of 3 |
| Total · 12 | 100% |