Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-027At risk4ExecutionHybrid

Irtiqaa Portal — Release 2

Add to watchlist

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-04-06⁩
Hijri
8 Shawwal 1446 AH
ApprovedDMD-2026-027Irtiqaa Portal — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-027
Project
Irtiqaa Portal — Release 2
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Qualification & Training Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Ghada A. Al-Shahrani

1The proposalAuto-filled

TitleAuto-filled
Irtiqaa Portal — Release 2
Proposed byAuto-filled
Ghada A. Al-Shahrani
DepartmentAuto-filled
Qualification Programmes & Capability Department
Submitted onAuto-filled
⁦2025-04-06⁩
Proposal numberAuto-filled
DMD-2026-027

2Justification

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

3Objectives

  1. Leadership and human capital

Strategic objectives served

  • SO-4.4 — Leadership and human capital

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 6.4M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 4.6M
Supervision & consultingSAR 900K
Internal teamSAR 600K
Contingency reserve (5%)SAR 300K
TotalSAR 6.4M

6Initial risks

RiskLevelProposed response
Low uptake of the Irtiqaa self-assessment among small contractorsMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2025-04-06⁩ 11:20
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-04-07⁩ 09:00
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-04-09⁩ 10:07
4Portfolio manager reviewTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-04-14⁩ 11:14
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-04-15⁩ 11:56
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2025-04-21⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-04-22⁩ 13:28

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-04-07⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-04-09⁩

Portfolio manager review

Dr. Noura M. Al-Otaibi

Approved⁦2025-04-14⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-04-15⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-04-22⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Ghada A. Al-Shahrani on ⁦2025-04-06⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-04-07⁩ at ⁦09:00⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-04-09⁩ at ⁦10:07⁩

  3. Technical acceptance

    Portfolio manager review

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-04-14⁩ at ⁦11:14⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-15⁩ at ⁦11:56⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-04-22⁩ at ⁦13:28⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-04-27⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Ghada A. Al-Shahrani

  2. V1Returned for edit⁦2025-04-06⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Ghada A. Al-Shahrani

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close