Smart Test-hall Proctoring & Access Control
Add to watchlist4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
SAR +4.7M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-24 | 2025-08-03 | +40 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-01 | 2025-12-10 | +70 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-26 | 2026-06-21 | +115 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-24 | 2026-12-22 | +151 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-10-31 | 2027-01-11 | +72 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
79%Awaiting acceptance
9%Not handed in
12%Deliverable flow
Display options
| Project plan & baseline013-D1 | 3% | CRT-013-01 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Eng. Bandar M. Al-Shammari | 2025-05-06 | V1 | 3 of 3 |
| Monitoring & reporting013-D2 | 3% | CRT-013-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2025-06-24 | V1 | 3 of 3 |
| Detailed design013-D3 | 6% | CRT-013-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2025-08-13 | V1 | 3 of 3 |
| Permits & approvals013-D4 | 6% | CRT-013-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2025-10-01 | V1 | 3 of 3 |
| Site works & excavation013-D5 | 13% | CRT-013-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2025-11-19 | V1 | 3 of 3 |
| Structure013-D6 | 13% | CRT-013-06 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Eng. Bandar M. Al-Shammari | 2026-01-08 | V1 | 3 of 3 |
| Finishes013-D7 | 13% | CRT-013-07 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-02-26 | V1 | 3 of 3 |
| Supply013-D8 | 11% | CRT-013-08 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | Eng. Bandar M. Al-Shammari | 2026-04-17 | V1 | 3 of 3 |
| Installation013-D9 | 11% | CRT-013-09 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-06-05 | V1 | 3 of 3 |
| Testing & commissioning013-D10 | 9% | — | Submitted | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2026-07-24 | V1 | 1 of 3 |
| Provisional acceptance013-D11 | 6% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-09-12 | V0 | 0 of 3 |
| Final acceptance013-D12 | 6% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2026-10-31 | V0 | 0 of 3 |
| Total · 12 | 100% |