Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-06-23⁩
Hijri
17 Dhuʻl-Hijjah 1445 AH
ApprovedDMD-2026-017Correspondence & Document Management System (DMS)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System (DMS)
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The proposalAuto-filled

TitleAuto-filled
Correspondence & Document Management System (DMS)
Proposed byAuto-filled
Dana S. Al-Saleh
DepartmentAuto-filled
Enterprise Systems & Integration Department
Submitted onAuto-filled
⁦2024-06-23⁩
Proposal numberAuto-filled
DMD-2026-017

2Justification

Automated correspondence, document management and e-archiving, linked to the government communications network.

3Objectives

  1. A mature operating model and accountability
  2. A sustainable financial base

Strategic objectives served

  • SO-4.2 — A mature operating model and accountability
  • SO-4.3 — A sustainable financial base

4Expected benefits

KindBenefit
Time savedFaster routing of correspondence — target 1.5 days

5Cost & feasibility

Estimated cost

SAR 14.2M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 10.2M
Supervision & consultingSAR 2M
Internal teamSAR 1.3M
Contingency reserve (5%)SAR 700K
TotalSAR 14.2M

6Initial risks

RiskLevelProposed response
High UAT defect count in the outgoing-mail moduleMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2024-06-23⁩ 10:43
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-06-25⁩ 14:53
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-06-26⁩ 09:00
4Portfolio manager reviewTechnical acceptanceEng. Nayef H. Al-BuqamiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-06-30⁩ 10:07
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-07-02⁩ 10:19
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-07-08⁩ 12:21

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-06-25⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-06-26⁩

Portfolio manager review

Eng. Nayef H. Al-Buqami

Approved⁦2024-06-30⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-07-02⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-07-08⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Dana S. Al-Saleh on ⁦2024-06-23⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-06-25⁩ at ⁦14:53⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-06-26⁩ at ⁦09:00⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Nayef H. Al-Buqami · Portfolio manager

    Approved · ⁦2024-06-30⁩ at ⁦10:07⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-07-02⁩ at ⁦10:19⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-07-08⁩ at ⁦12:21⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-07-14⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Dana S. Al-Saleh

  2. V1Returned for edit⁦2024-06-23⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Dana S. Al-Saleh

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close