PRJ-2026-020Off track4ExecutionConstruction

Qassim Vocational Qualification Centre

Remove from watchlist

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Periodic update — August 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
SCA-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-09-02⁩
Hijri
20 Rabiʻ I 1448 AH
ApprovedUPD-020-2026-08Periodic update — August 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
Qassim Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ahmed Y. Asiri

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦39%⁩

Planned to date

⁦48%⁩

SPI

0.82

Actual cost

SAR 140.6M

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

2Status

Overall healthAuto-filled
Off track
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2027-08-03⁩

The PM’s comment on the statusFilled by the project manager

The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
RSK-0034Unforeseen ground conditions and groundwater at the foundations of axes 12 to 1620Eng. Ahmed Y. Asiri
RSK-0035Pile lengths exceeding contract quantities12Eng. Ahmed Y. Asiri
CodeImpedimentSeverity
ISS-0123Excavation at axis 14 stopped by groundwaterHigh

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

Approve change request CR-2026-012 for three integration engineers (SAR 980K), and the Secretary-General to press the NIC on the Nafath environment.

Includes financial supportAuto-filled
Yes

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction ProjectsSubmitted—⁦2026-09-02⁩ 14:11
2PMO checkMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedThe reading agrees with the schedule and finance.⁦2026-09-06⁩ 10:37
3Sponsor review & approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2026-09-07⁩ 11:44

Signatures

PMO check

Ghada A. Al-Shahrani

Approved⁦2026-09-06⁩

Sponsor review & approval

Eng. Turki A. Al-Anazi

Approved⁦2026-09-07⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2026-09-02⁩

  1. Methodology review

    PMO check

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-06⁩ at ⁦10:37⁩

    The reading agrees with the schedule and finance.

  2. Technical acceptance

    Sponsor review & approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2026-09-07⁩ at ⁦11:44⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-09-02⁩

    The card as the PM filled it

    Eng. Ahmed Y. Asiri

Only one version so far.