Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-026On hold3PlanningWaterfall

Energy Retrofit of Existing SCA Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-07-06⁩
Hijri
11 Muharram 1447 AH
ApprovedDMD-2026-026Energy Retrofit of Existing SCA Buildings (ESCO)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Energy Retrofit of Existing SCA Buildings (ESCO)
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1The proposalAuto-filled

TitleAuto-filled
Energy Retrofit of Existing SCA Buildings (ESCO)
Proposed byAuto-filled
Eng. Mishari K. Al-Otaibi
DepartmentAuto-filled
Sustainability & Energy Efficiency Department
Submitted onAuto-filled
⁦2025-07-06⁩
Proposal numberAuto-filled
DMD-2026-026

2Justification

HVAC and lighting retrofits in 34 owned and leased SCA buildings through ESCOs on performance contracts.

3Objectives

  1. Efficient, sustainable SCA facilities
  2. A sustainable financial base

Strategic objectives served

  • SO-3.2 — Efficient, sustainable SCA facilities
  • SO-4.3 — A sustainable financial base

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 33M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 23.8M
Supervision & consultingSAR 4.5M
Internal teamSAR 3M
Contingency reserve (5%)SAR 1.7M
TotalSAR 33M

6Initial risks

RiskLevelProposed response
Funding left out of the 2027 budget, keeping the tender suspendedHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencySubmitted—⁦2025-07-06⁩ 10:13
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-07-08⁩ 14:23
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-07-09⁩ 09:30
4Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-07-13⁩ 10:37
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2025-07-16⁩ 08:00
6Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-07-17⁩ 10:49
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-07-23⁩ 12:51

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-07-08⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-07-09⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2025-07-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-07-17⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-07-23⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2025-07-06⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-07-08⁩ at ⁦14:23⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-07-09⁩ at ⁦09:30⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-07-13⁩ at ⁦10:37⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-07-17⁩ at ⁦10:49⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-07-23⁩ at ⁦12:51⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-07-27⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for edit⁦2025-07-06⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Mishari K. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close