PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-09-10⁩
Hijri
25 Safar 1445 AH
ApprovedDMD-2026-031Electronic Model Contracts

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Electronic Model Contracts
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1The proposalAuto-filled

TitleAuto-filled
Electronic Model Contracts
Proposed byAuto-filled
Karim Haddad
DepartmentAuto-filled
Model Contracts & Regulatory Guides Department
Submitted onAuto-filled
⁦2023-09-10⁩
Proposal numberAuto-filled
DMD-2026-031

2Justification

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

3Objectives

  1. Simplify regulatory relationships and make doing business easier

Strategic objectives served

  • SO-1.1 — Simplify regulatory relationships and make doing business easier

4Expected benefits

KindBenefit
Time savedShorter time to sign and register a contract — target 15 minutes
SatisfactionHigher contractor satisfaction with signing and registering contracts — target 85 %

5Cost & feasibility

Estimated cost

SAR 8.2M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 5.9M
Supervision & consultingSAR 1.2M
Internal teamSAR 700K
Contingency reserve (5%)SAR 400K
TotalSAR 8.2M

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2023-09-10⁩ 12:15
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-09-12⁩ 10:25
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-09-17⁩ 11:32
4Portfolio manager reviewTechnical acceptanceFaisal A. Al-ShehriPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-09-18⁩ 12:39
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-09-20⁩ 12:51
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2023-09-26⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-09-27⁩ 14:53

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-09-12⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-09-17⁩

Portfolio manager review

Faisal A. Al-Shehri

Approved⁦2023-09-18⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-09-20⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-09-27⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Karim Haddad on ⁦2023-09-10⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-09-12⁩ at ⁦10:25⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-09-17⁩ at ⁦11:32⁩

  3. Technical acceptance

    Portfolio manager review

    Faisal A. Al-Shehri · Portfolio manager

    Approved · ⁦2023-09-18⁩ at ⁦12:39⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-09-20⁩ at ⁦12:51⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-09-27⁩ at ⁦14:53⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-10-01⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Karim Haddad

  2. V1Returned for edit⁦2023-09-10⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Karim Haddad

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close