Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2024-04-14⁩
Hijri
5 Shawwal 1445 AH
ApprovedMTG-KO-031Kick-off — Electronic Model Contracts

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Electronic Model Contracts
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Electronic Model Contracts
Date and timeAuto-filled
⁦2024-04-14⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Karim Haddad

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Majed S. Al-RasheedHead, Digital Transformation Sector
Faisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio Manager
Karim HaddadSenior Digital Delivery Consultant — PMO
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Eng. Majed S. Al-RasheedProject sponsorSponsors the project, decides escalations and material changes
Faisal A. Al-ShehriProject ownerApproves the requirements and accepts the deliverables
Karim HaddadProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates

3Tasks

TaskOwnerDueStatus
Project plan approvedKarim Haddad⁦2024-07-17⁩Done
Designs approvedKarim Haddad⁦2024-10-02⁩Done
Build completeKarim Haddad⁦2025-01-26⁩Done
Testing & acceptance completeKarim Haddad⁦2025-04-14⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2024-06-18⁩
Start confirmed
Eng. Majed S. Al-Rasheed · ⁦2024-04-15⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2024-04-15⁩ 09:12
2Chair’s approval (sponsor)Technical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2024-04-16⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-04-16⁩ 13:16

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2024-04-16⁩

Chair’s approval (sponsor)

Eng. Majed S. Al-Rasheed

Approved⁦2024-04-16⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Karim Haddad on ⁦2024-04-15⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-04-16⁩ at ⁦13:16⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2024-04-16⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-04-14⁩

    The minutes as taken

    Karim Haddad

Only one version so far.