PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work8M⁦16⁩ elements
Unallocated contingency246KSAR 410K
Budget at completion8.2MPRJ-2026-031
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project469⁦2024-04-07⁩⁦2025-07-20⁩⁦100%⁩7.957.96—
1
Phase105⁦2024-04-07⁩⁦2024-07-21⁩⁦100%⁩0.640.64—
1.1
WBS element65⁦2024-04-07⁩⁦2024-06-11⁩⁦100%⁩0.320.320 / 1
1.2
WBS element65⁦2024-05-17⁩⁦2024-07-21⁩⁦100%⁩0.320.321 / 2
2
Phase105⁦2024-06-27⁩⁦2024-10-10⁩⁦100%⁩1.351.35—
2.1
WBS element65⁦2024-06-27⁩⁦2024-08-31⁩⁦100%⁩0.680.681 / 1
2.2
WBS element65⁦2024-08-06⁩⁦2024-10-10⁩⁦100%⁩0.680.681 / 2
3
Phase145⁦2024-09-16⁩⁦2025-02-08⁩⁦100%⁩3.183.18—
3.1
WBS element64⁦2024-09-16⁩⁦2024-11-19⁩⁦100%⁩1.061.061 / 1
3.2
WBS element65⁦2024-10-26⁩⁦2024-12-30⁩⁦100%⁩1.061.061 / 1
3.3
WBS element64⁦2024-12-06⁩⁦2025-02-08⁩⁦100%⁩1.061.061 / 2
4
Phase105⁦2025-01-15⁩⁦2025-04-30⁩⁦100%⁩1.591.59—
4.1
WBS element65⁦2025-01-15⁩⁦2025-03-21⁩⁦100%⁩0.800.801 / 1
4.2
WBS element65⁦2025-02-24⁩⁦2025-04-30⁩⁦100%⁩0.800.801 / 2
5
Phase105⁦2025-04-06⁩⁦2025-07-20⁩⁦100%⁩1.191.19—
5.1
WBS element65⁦2025-04-06⁩⁦2025-06-10⁩⁦100%⁩0.600.601 / 1
5.2
WBS element65⁦2025-05-16⁩⁦2025-07-20⁩⁦100%⁩0.600.601 / 1
Total⁦100%⁩7.957.96