PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
SCA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-04-12⁩
Hijri
24 Shawwal 1447 AH
ApprovedCR-2026-011Redesign training halls for e-testing

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Jeddah Branch & Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Fahad T. Al-Sulami

1The change

TitleAuto-filled
Redesign training halls for e-testing
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Fahad T. Al-Sulami
Raised onAuto-filled
⁦2026-04-12⁩

Reason

Electronic skills testing needs halls with proctoring, recording and an isolated network the design left out

Justification

Changing it now is cheaper than refitting 40 halls after opening

2Impact analysis

Cost

SAR +9.6M

Schedule

+20 days

Risk

9 → 6

Benefits

+6%

Risk impact

Removes the risk of refitting after opening

Benefits impact

40 halls ready for e-testing from day one

3The approval decision

The PMO’s recommendation

The PMO recommends approval

Change Committee decision
Approve
Decided on
⁦2026-04-21⁩
Decision number
DEC-2026-033

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Fahad T. Al-SulamiDirector, Regional Qualification CentresSubmitted—⁦2026-04-12⁩ 11:56
2Project managerTechnical acceptanceEng. Fahad T. Al-SulamiProject managerApproved—⁦2026-04-13⁩ 13:40
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-04-15⁩ 14:47
4Financial impactFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-04-19⁩ 12:15
5Contractual impactFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-04-20⁩ 13:52
6Change CommitteeTechnical acceptanceDr. Mohammed I. Al-SubaieChange CommitteeApproved—⁦2026-04-23⁩ 11:08

Signatures

Project manager

Eng. Fahad T. Al-Sulami

Approved⁦2026-04-13⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-04-15⁩

Financial impact

Munirah A. Al-Khalidi

Approved⁦2026-04-19⁩

Contractual impact

Mazen A. Al-Hazmi

Approved⁦2026-04-20⁩

Change Committee

Dr. Mohammed I. Al-Subaie

Approved⁦2026-04-23⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Fahad T. Al-Sulami on ⁦2026-04-12⁩

  1. Technical acceptance

    Project manager

    Eng. Fahad T. Al-Sulami · Project manager

    Approved · ⁦2026-04-13⁩ at ⁦13:40⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-04-15⁩ at ⁦14:47⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-04-19⁩ at ⁦12:15⁩

  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-04-20⁩ at ⁦13:52⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Approved · ⁦2026-04-23⁩ at ⁦11:08⁩

Steps that do not apply to this record

  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-04-21⁩

    Approved by the committee

    Eng. Fahad T. Al-Sulami

  2. V1Returned for edit⁦2026-04-12⁩

    The request as raised

    Eng. Fahad T. Al-Sulami