Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- SCA-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-04-12
- Hijri
- 24 Shawwal 1447 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-006
- Project
- Jeddah Branch & Qualification Centre
- Portfolio
- Academy & Qualification Centres Portfolio
- Sector
- Qualification & Training Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Fahad T. Al-Sulami
1The change
- TitleAuto-filled
- Redesign training halls for e-testing
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Fahad T. Al-Sulami
- Raised onAuto-filled
- 2026-04-12
Reason
Electronic skills testing needs halls with proctoring, recording and an isolated network the design left out
Justification
Changing it now is cheaper than refitting 40 halls after opening
2Impact analysis
Cost
SAR +9.6M
Schedule
+20 days
Risk
9 → 6
Benefits
+6%
Risk impact
Removes the risk of refitting after opening
Benefits impact
40 halls ready for e-testing from day one
3The approval decision
The PMO’s recommendation
The PMO recommends approval
- Change Committee decision
- Approve
- Decided on
- 2026-04-21
- Decision number
- DEC-2026-033
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Fahad T. Al-SulamiDirector, Regional Qualification Centres | Submitted | — | 2026-04-12 11:56 |
| 2 | Project manager | Technical acceptance | Eng. Fahad T. Al-SulamiProject manager | Approved | — | 2026-04-13 13:40 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-04-15 14:47 |
| 4 | Financial impact | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2026-04-19 12:15 |
| 5 | Contractual impact | Financial approval | Mazen A. Al-HazmiProcurement & contracts | Approved | — | 2026-04-20 13:52 |
| 6 | Change Committee | Technical acceptance | Dr. Mohammed I. Al-SubaieChange Committee | Approved | — | 2026-04-23 11:08 |
Signatures
Project manager
Eng. Fahad T. Al-Sulami
Approved2026-04-13
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-04-15
Financial impact
Munirah A. Al-Khalidi
Approved2026-04-19
Contractual impact
Mazen A. Al-Hazmi
Approved2026-04-20
Change Committee
Dr. Mohammed I. Al-Subaie
Approved2026-04-23