Original
Original baseline
- Finish
- 2026-11-30
- Budget
- SAR 18.4M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-05-04 · by Dr. Mohammed I. Al-Subaie
A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.
Budget (BAC)
Actual cost
89% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-05-04 · by Dr. Mohammed I. Al-Subaie
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Karim Haddad
What changed from version A to version B
Finish
2026-11-302026-11-30
0 days
Budget
SAR 18.4MSAR 18.4M
0.00 SAR M
Milestones moved
4 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference