PRJ-2026-008On track4ExecutionScrum

Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

Wifaq Dispute Settlement Platform — Release 2

APPROVEDV2Approved ⁦2025-05-02⁩

1Project identity

Required at this stage
Project name
Wifaq Dispute Settlement Platform — Release 2
Project code
PRJ-2026-008
Project sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.sa
Project manager
Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa
Project owner
Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa
Portfolio & programme
Digital Services & Platforms PortfolioMuqawil & e-Services Programme
Type & methodology
Digital · Scrum
Current phase
4Execution

2Background & rationale

Required at this stage

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

3Objectives

Required at this stage
  1. 1Build capability and innovation in the sector
  2. 2Raise quality standards across contracting

4Scope

Required at this stage

In scope

  • A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Single sign-on through Nafath
  2. 2Integration with internal systems
  3. 3Digital Government Authority standards

6Deliverables

Required at this stage
1Project management plan⁦2025-05-27⁩
2Main deliverable — stage 1⁦2026-02-22⁩
3Main deliverable — final stage⁦2026-09-11⁩
4Final report⁦2026-11-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-05-02⁩
  2. Contract signed⁦2025-08-04⁩
  3. 50% of works complete⁦2026-02-22⁩
  4. Provisional acceptance⁦2026-10-15⁩
  5. Closure⁦2026-11-30⁩

8Budget

Required at this stage
  • Main contract⁦71.7%⁩13.2M
  • Supervision & consulting⁦14.1%⁩2.6M
  • Internal team⁦9.2%⁩1.7M
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩900K
The owning sector’s approved budgetTotal18.4M

9Timeline

Required at this stage
Start
2025-05-046 Dhuʻl-Qiʻdah 1446 AH
Baseline finish
2026-11-3020 Jumada II 1448 AH
Duration
⁦19⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board