PRJ-2026-008On track4ExecutionScrum
Wifaq Dispute Settlement Platform — Release 2
Add to watchlistA platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.
Project managerKarim HaddadProject sponsorDr. Mohammed I. Al-SubaieProgrammeMuqawil & e-Services Programme
Budget (BAC)
SAR 18.4M
Actual cost
SAR 16.4M
89% of budget
Progress
91%Awaiting acceptance 5%
Estimate at completion
SAR 18M
SPI · CPI
1.01Schedule performance index · 1.011.02Cost performance index · 1.02
Forecast finish
2026-11-26
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-008-2026-10 | Draft | 91% | — | 2026-10-26 |
| September 2026UPD-008-2026-09 | Approved | 86% | — | 2026-10-02 |
| August 2026UPD-008-2026-08 | Approved | 81% | — | 2026-09-02 |