Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-008On track4ExecutionScrum

Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 18.4M split into spent, committed and left, with the estimate at completion

EAC SAR 18M
Revised request SAR 18.4M
  • Actual spendSAR 16.4M
  • Committed, not spentSAR 484K
  • Allotted, uncommittedSAR 948K
  • Contingency availableSAR 552K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 17.1M
Original budgetwhen the first baseline was approved
SAR 18.4M
Approved budgetafter approved change requests
SAR 18.4M
Current budgetavailable to spend now
SAR 18.4M
Revised budgetif the pending changes are approved
SAR 18.4M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 16.9M
Contracts1 active contract
SAR 14.8M
Purchase orders⁦2⁩ orders
SAR 2.1M
Remaining budgetapproved less actual
SAR 2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 16.4M
Accrualswork done, not yet invoiced
SAR 657K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 18M
ContingencySAR 368K drawn of SAR 920K
SAR 552K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 17.1M
ApprovedSAR 18.4M
Estimate at completionSAR 18M
Approved is SAR 1.3M (⁦7.6%⁩) above the estimate
The estimate at completion is SAR 939K (⁦5.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-02-18⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-31008
  • WBS elements⁦5⁩ elements · P-2026-008.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦11⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 368K drawn of SAR 920K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 368K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.431.441.441.44⁦−0.02⁩
2Analysis & design3.033.073.073.07⁦−0.03⁩
3Build7.147.227.227.22⁦−0.08⁩
4Testing & acceptance3.573.613.613.61⁦−0.04⁩
5Launch & handover2.681.571.082.43⁦+0.25⁩
Unallocated contingency0.550.000.000.28⁦+0.28⁩
Total18.4016.9016.4218.04⁦+0.36⁩

Budget split

WBS

SAR 18.4M

Budget

  • Management & governanceSAR 1.4M⁦8%⁩
  • Analysis & designSAR 3M⁦16%⁩
  • BuildSAR 7.1M⁦39%⁩
  • Testing & acceptanceSAR 3.6M⁦19%⁩
  • Launch & handoverSAR 2.7M⁦15%⁩
  • Unallocated contingencySAR 552K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-03-02⁩+92

SPI(t) ⁦0.86⁩ against the approved finish ⁦2026-11-30⁩

Planned valuePV
SAR 18.3M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 16.7M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 16.4M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 18.4M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.33⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1.51⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.92
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 18M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 1.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.36⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.83
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 18M
  • If the rest goes to planSAR 18.1M
  • At cost and schedule performanceSAR 18.2M
  • The PM’s bottom-up estimateSAR 18M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 18M

Variance at completion: ⁦+0.36⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close