Wifaq Dispute Settlement Platform — Release 2
Add to watchlistA platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.
Budget (BAC)
Actual cost
89% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started