Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
SCA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-05-02⁩
Hijri
4 Dhuʻl-Qiʻdah 1446 AH
ApprovedPRJ-2026-008Wifaq Dispute Settlement Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
Wifaq Dispute Settlement Platform — Release 2
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Karim Haddad

1Objective

Background

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Project objectives

  1. Build capability and innovation in the sector
  2. Raise quality standards across contracting

2Scope

In scope

  • A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-05-27⁩
Main deliverable — stage 1⁦2026-02-22⁩
Main deliverable — final stage⁦2026-09-11⁩
Final report⁦2026-11-30⁩
MilestoneDate
Charter approved⁦2025-05-02⁩
Contract signed⁦2025-08-04⁩
50% of works complete⁦2026-02-22⁩
Provisional acceptance⁦2026-10-15⁩
Closure⁦2026-11-30⁩

4RolesAuto-filled

SponsorAuto-filled
Dr. Mohammed I. Al-Subaie
Project ownerAuto-filled
Yousef A. Al-Omari
Project managerAuto-filled
Karim Haddad
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change Control BoardApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 13.2M
Supervision & consultingSAR 2.6M
Internal teamSAR 1.7M
Contingency reserve (5%)SAR 900K
Approved budgetSAR 18.4M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2025-04-23⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-04-26⁩ 12:30
3Project ownerTechnical acceptanceYousef A. Al-OmariProject ownerApproved—⁦2025-04-29⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-04-30⁩ 11:10
5Sponsor approvalTechnical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-05-02⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-04-26⁩

Project owner

Yousef A. Al-Omari

Approved⁦2025-04-29⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-04-30⁩

Sponsor approval

Dr. Mohammed I. Al-Subaie

Approved⁦2025-05-02⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Karim Haddad on ⁦2025-04-23⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-04-26⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Yousef A. Al-Omari · Project owner

    Approved · ⁦2025-04-29⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-30⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-05-02⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-05-02⁩

    Approved version

    • PMO comments addressed

    Karim Haddad

  2. V1Returned for edit⁦2025-04-13⁩

    First draft

    • Returned to detail the budget

    Karim Haddad