Project status card
28 October 2026 · 17 Jumada I 1448 AH
Wifaq Dispute Settlement Platform — Release 2
PRJ-2026-008 · Regulation & Development Sector · Strategic · WP-2025-008
- Progress
- 91% / 90%
- SPI · CPI
- 1.01 · 1.02
- Spend
- SAR 16.4M / SAR 18.4M
- Estimate at completion
- SAR 18M
Schedule
Planned to date 90%
Forecast finish: 2026-11-2616 Jumada II 1448 AH · On time
SPI1.01Schedule performance index · 1.01CPI1.02Cost performance index · 1.02Health dimensions
Last update: 2026-10-2716 Jumada I 1448 AH · Up to date
Deliverables
7 of 10 due deliverables accepted on time (70%)
Next milestones
- Final handover2026-11-3020 Jumada II 1448 AH
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 18.4M: 1 on track and 0 red or critical. Weighted progress is 91% against 90% planned, spend SAR 16.4M, and EAC SAR 18M (SAR 0.4M under).
No project is more than a month behind baseline.