PRJ-2026-008On track4ExecutionScrum

Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Wifaq Dispute Settlement Platform — Release 2

PRJ-2026-008 · Regulation & Development Sector · Strategic · WP-2025-008

On track4ExecutionProject manager: Karim Haddad · Sponsor: Dr. Mohammed I. Al-Subaie
Progress
⁦91%⁩ / ⁦90%⁩
SPI · CPI
1.01 · 1.02
Spend
SAR 16.4M / SAR 18.4M
Estimate at completion
SAR 18M

Schedule

⁦1%⁩ ahead⁦91%⁩

Planned to date ⁦90%⁩

Forecast finish: 2026-11-2616 Jumada II 1448 AH · On time

SPI1.01Schedule performance index · 1.01CPI1.02Cost performance index · 1.02

Health dimensions

On track

Last update: 2026-10-2716 Jumada I 1448 AH · Up to date

Deliverables

⁦7⁩ of ⁦10⁩ due deliverables accepted on time (⁦70%⁩)

Next milestones

  • Final handover2026-11-3020 Jumada II 1448 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 18.4M: 1 on track and 0 red or critical. Weighted progress is 91% against 90% planned, spend SAR 16.4M, and EAC SAR 18M (SAR 0.4M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Karim Haddad in MunjazInternal