Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-008On track4ExecutionScrum

Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-07-07⁩
Hijri
22 Muharram 1448 AH
ApprovedCRT-008-07Integrations

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
Wifaq Dispute Settlement Platform — Release 2
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Karim Haddad

1The deliverableAuto-filled

DeliverableAuto-filled
Integrations
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Yousef A. Al-Omari
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦14%⁩
DueAuto-filled
⁦2026-05-16⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-008_3.3_v1.pdfV1Yousef A. Al-Omari⁦2026-04-08⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Yousef A. Al-Omari
Accepted byAuto-filled
Dr. Mohammed I. Al-Subaie
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2025-010
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Yousef A. Al-OmariDirector General, Partnerships & EventsSubmitted—⁦2026-04-08⁩ 12:21
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-04-12⁩ 14:23
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Mohammed I. Al-SubaieProject ownerOn behalf of Yousef A. Al-OmariApprovedInspected and accepted against the approved acceptance criteria.⁦2026-04-13⁩ 09:30
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-04-14⁩ 13:40
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-04-16⁩ 14:17

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-04-12⁩

Inspection & technical acceptance — owner

Dr. Mohammed I. Al-Subaie

Approved⁦2026-04-13⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-04-14⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-04-16⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Yousef A. Al-Omari on ⁦2026-04-08⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-04-12⁩ at ⁦14:23⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Yousef A. Al-Omari · Project owner

    Approved · ⁦2026-04-13⁩ at ⁦09:30⁩ · On behalf of Yousef A. Al-Omari (Dr. Mohammed I. Al-Subaie)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-04-14⁩ at ⁦13:40⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-04-16⁩ at ⁦14:17⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-04-08⁩

    PRJ-2026-008_3.3_v1.pdf

    Yousef A. Al-Omari

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close