PRJ-2026-008On track4ExecutionScrum

Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-10-06⁩
Hijri
3 Rabiʻ II 1446 AH
ApprovedDMD-2026-008Wifaq Dispute Settlement Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
Wifaq Dispute Settlement Platform — Release 2
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Karim Haddad

1The proposalAuto-filled

TitleAuto-filled
Wifaq Dispute Settlement Platform — Release 2
Proposed byAuto-filled
Karim Haddad
DepartmentAuto-filled
Wifaq Dispute Settlement Centre
Submitted onAuto-filled
⁦2024-10-06⁩
Proposal numberAuto-filled
DMD-2026-008

2Justification

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

3Objectives

  1. Build capability and innovation in the sector
  2. Raise quality standards across contracting

Strategic objectives served

  • SO-2.1 — Build capability and innovation in the sector
  • SO-1.2 — Raise quality standards across contracting

4Expected benefits

KindBenefit
ProductivitySettlement requests completed online — target 900 requests

5Cost & feasibility

Estimated cost

SAR 18.4M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 13.2M
Supervision & consultingSAR 2.6M
Internal teamSAR 1.7M
Contingency reserve (5%)SAR 900K
TotalSAR 18.4M

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2024-10-06⁩ 10:13
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-10-08⁩ 14:23
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-10-09⁩ 09:30
4Portfolio manager reviewTechnical acceptanceFaisal A. Al-ShehriPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-10-13⁩ 10:37
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2024-10-16⁩ 08:00
6Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-10-17⁩ 10:49
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-10-23⁩ 12:51

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-10-08⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-10-09⁩

Portfolio manager review

Faisal A. Al-Shehri

Approved⁦2024-10-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-10-17⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-10-23⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Karim Haddad on ⁦2024-10-06⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-10-08⁩ at ⁦14:23⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-10-09⁩ at ⁦09:30⁩

  3. Technical acceptance

    Portfolio manager review

    Faisal A. Al-Shehri · Portfolio manager

    Approved · ⁦2024-10-13⁩ at ⁦10:37⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-10-17⁩ at ⁦10:49⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-10-23⁩ at ⁦12:51⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-10-27⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Karim Haddad

  2. V1Returned for edit⁦2024-10-06⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Karim Haddad