PRJ-2026-008On track4ExecutionScrum

Wifaq Dispute Settlement Platform — Release 2

Add to watchlist

A platform to file contracting disputes online, assign them to accredited mediators and follow the settlement sessions until the agreement is signed.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-05-11⁩
Hijri
13 Dhuʻl-Qiʻdah 1446 AH
ApprovedMTG-KO-008Kick-off — Wifaq Dispute Settlement Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
Wifaq Dispute Settlement Platform — Release 2
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Karim Haddad

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Wifaq Dispute Settlement Platform — Release 2
Date and timeAuto-filled
⁦2025-05-11⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Karim Haddad

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence Sector
Yousef A. Al-OmariDirector General, Partnerships & Events
Karim HaddadSenior Digital Delivery Consultant — PMO
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Yousef A. Al-OmariDirector General, Partnerships & Events
Eng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-Services
Hala F. Al-AngariDirector General, Regulation & Model Contracts

2Roles

PersonRoleDuty
Dr. Mohammed I. Al-SubaieProject sponsorSponsors the project, decides escalations and material changes
Yousef A. Al-OmariProject ownerApproves the requirements and accepts the deliverables
Karim HaddadProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Yousef A. Al-OmariOwner of the partner-agency procedures, WifaqDelivers their tasks and uploads the evidence
Eng. Reem K. Al-DosariProgramme oversight, WifaqDelivers their tasks and uploads the evidence
Hala F. Al-AngariProject ownerDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedKarim Haddad⁦2025-09-10⁩Done
Designs approvedKarim Haddad⁦2025-12-18⁩Done
Build completeKarim Haddad⁦2026-05-16⁩Done
Testing & acceptance completeKarim Haddad⁦2026-08-23⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-08-04⁩
Start confirmed
Dr. Mohammed I. Al-Subaie · ⁦2025-05-12⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2025-05-12⁩ 13:10
2Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-05-13⁩ 11:14
3Chair’s approval (sponsor)Technical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-05-13⁩ 12:30

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-05-13⁩

Chair’s approval (sponsor)

Dr. Mohammed I. Al-Subaie

Approved⁦2025-05-13⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Karim Haddad on ⁦2025-05-12⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-05-13⁩ at ⁦11:14⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-05-13⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-05-11⁩

    The minutes as taken

    Karim Haddad

Only one version so far.