Wifaq Dispute Settlement Platform — Release 2 Subtask Last item under this branch 2026-11-30 91% Wifaq Dispute Settlement Platform — Release 2 Planned: 2025-05-04 → 2026-11-30 Forecast: 2025-05-04 → 2026-11-30 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-09-28 100% Management & governance Planned: 2025-05-04 → 2025-09-10 Actual: 2025-05-04 → 2025-09-28
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-02 100% Project plan & baseline Planned: 2025-05-04 → 2025-07-22 Actual: 2025-05-04 → 2025-08-02
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-28 100% Monitoring & reporting Planned: 2025-06-23 → 2025-09-10 Actual: 2025-06-29 → 2025-09-28
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-28 100% Project plan approved Planned: 2025-09-10 → 2025-09-10 Actual: 2025-09-28 → 2025-09-28 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-01-19 100% Analysis & design Planned: 2025-08-11 → 2025-12-18 Actual: 2025-08-25 → 2026-01-19
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-11-23 100% Business requirements Planned: 2025-08-11 → 2025-10-29 Actual: 2025-08-25 → 2025-11-23
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-19 100% Solution design Planned: 2025-09-30 → 2025-12-18 Actual: 2025-10-20 → 2026-01-19
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-19 100% Designs approved Planned: 2025-12-18 → 2025-12-18 Actual: 2026-01-19 → 2026-01-19 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-07-07 100% Build Planned: 2025-11-18 → 2026-05-16 Actual: 2025-12-16 → 2026-07-07
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-16 100% Release 1 Planned: 2025-11-18 → 2026-02-06 Actual: 2025-12-16 → 2026-03-16
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-12 100% Release 2 Planned: 2026-01-07 → 2026-03-27 Actual: 2026-02-10 → 2026-05-12
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-07 100% Integrations Planned: 2026-02-25 → 2026-05-16 Actual: 2026-04-08 → 2026-07-07
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-07 100% Build complete Planned: 2026-05-16 → 2026-05-16 Actual: 2026-07-07 → 2026-07-07 Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Testing & acceptance Planned: 2026-04-16 → 2026-08-23 Actual: 2026-06-03 → 2026-10-26
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-09-01 100% System testing Planned: 2026-04-16 → 2026-07-04 Actual: 2026-06-03 → 2026-09-01
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% User acceptance testing Planned: 2026-06-05 → 2026-08-23 Actual: 2026-07-30 → 2026-10-26
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Testing & acceptance complete Planned: 2026-08-23 → 2026-08-23 Actual: 2026-10-26 → 2026-10-26 Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-30 40% Launch & handover Planned: 2026-07-24 → 2026-11-30 Forecast: 2026-07-24 → 2026-11-30 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-13 80% Training & change Planned: 2026-07-24 → 2026-10-11 Forecast: 2026-07-24 → 2026-11-13 Float: 4d Drag to change its duration +33
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-26 0% Go-live & handover Planned: 2026-09-12 → 2026-11-30 Forecast: 2026-11-05 → 2026-11-26 Float: 4d Drag to change its dates
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-30 0% Final handover Planned: 2026-11-30 → 2026-11-30 Forecast: 2026-11-30 → 2026-11-30 Float: 0d Drag to change its dates Final handover