Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+11⁩ days vs approved

Baseline (original = approved)⁦2027-02-28⁩
Current forecast⁦2027-03-11⁩
By earned schedule⁦2028-05-18⁩
Critical activities
7
of ⁦9⁩ open activities
Late activities
6
past their baseline finish
Schedule performance
0.56
earned ÷ planned value
Next milestone
in 29 days
Build complete
Expand allCollapse all
Activity
Hail Vocational Qualification CentrePlanned: ⁦2025-03-16⁩ → ⁦2027-02-28⁩Forecast: ⁦2025-03-16⁩ → ⁦2027-03-11⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-03-16⁩ → ⁦2025-08-10⁩Actual: ⁦2025-03-16⁩ → ⁦2025-11-04⁩
Project plan & baselinePlanned: ⁦2025-03-16⁩ → ⁦2025-06-15⁩Actual: ⁦2025-03-16⁩ → ⁦2025-08-06⁩
Monitoring & reportingPlanned: ⁦2025-05-12⁩ → ⁦2025-08-10⁩Actual: ⁦2025-06-14⁩ → ⁦2025-11-04⁩
Project plan approvedPlanned: ⁦2025-08-10⁩ → ⁦2025-08-10⁩Actual: ⁦2025-11-04⁩ → ⁦2025-11-04⁩Project plan approved
Design & permitsPlanned: ⁦2025-07-07⁩ → ⁦2025-12-02⁩Actual: ⁦2025-09-11⁩ → ⁦2026-05-02⁩
Detailed designPlanned: ⁦2025-07-07⁩ → ⁦2025-10-06⁩Actual: ⁦2025-09-11⁩ → ⁦2026-02-01⁩
Permits & approvalsPlanned: ⁦2025-09-02⁩ → ⁦2025-12-02⁩Actual: ⁦2025-12-10⁩ → ⁦2026-05-02⁩
Designs approvedPlanned: ⁦2025-12-02⁩ → ⁦2025-12-02⁩Actual: ⁦2026-05-02⁩ → ⁦2026-05-02⁩Designs approved
Civil worksPlanned: ⁦2025-10-29⁩ → ⁦2026-05-21⁩Forecast: ⁦2026-02-19⁩ → ⁦2026-11-26⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2025-10-29⁩ → ⁦2026-01-27⁩Actual: ⁦2026-03-09⁩ → ⁦2026-07-30⁩
StructurePlanned: ⁦2025-12-24⁩ → ⁦2026-03-25⁩Actual: ⁦2026-06-07⁩ → ⁦2026-10-26⁩
FinishesPlanned: ⁦2026-02-19⁩ → ⁦2026-05-21⁩Forecast: ⁦2026-02-19⁩ → ⁦2026-11-26⁩Float: ⁦0⁩dDrag to change its duration+189
Build completePlanned: ⁦2026-05-21⁩ → ⁦2026-05-21⁩Forecast: ⁦2026-11-26⁩ → ⁦2026-11-26⁩Float: ⁦105⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2026-04-17⁩ → ⁦2026-11-07⁩Forecast: ⁦2026-11-13⁩ → ⁦2027-01-28⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-04-17⁩ → ⁦2026-07-16⁩Forecast: ⁦2026-11-13⁩ → ⁦2026-12-17⁩Float: ⁦0⁩dDrag to change its dates+154
InstallationPlanned: ⁦2026-06-12⁩ → ⁦2026-09-11⁩Forecast: ⁦2026-12-04⁩ → ⁦2027-01-07⁩Float: ⁦0⁩dDrag to change its dates+118
Testing & commissioningPlanned: ⁦2026-08-08⁩ → ⁦2026-11-07⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-01-28⁩Float: ⁦0⁩dDrag to change its dates+82
Testing & acceptance completePlanned: ⁦2026-11-07⁩ → ⁦2026-11-07⁩Forecast: ⁦2027-01-28⁩ → ⁦2027-01-28⁩Float: ⁦42⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2026-10-04⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-01-15⁩ → ⁦2027-03-11⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-10-04⁩ → ⁦2027-01-02⁩Forecast: ⁦2027-01-15⁩ → ⁦2027-02-18⁩Float: ⁦0⁩dDrag to change its dates+47
Final acceptancePlanned: ⁦2026-11-29⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-02-05⁩ → ⁦2027-03-11⁩Float: ⁦0⁩dDrag to change its dates+11
Final handoverPlanned: ⁦2027-02-28⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-03-11⁩ → ⁦2027-03-11⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦9⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦6⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Finishes” needs a pace ⁦4.1⁩× faster than it has kept

It earned ⁦68%⁩ in 251 days; the forecast assumes the rest in 29 days. At the pace so far it finishes on ⁦2027-02-23⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 127 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

86
151
189
82
G1G2G3G4

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close