Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Muqawil Platform — Release 4

PRJ-2026-014 · Digital Transformation Sector · Strategic · WP-2025-014

At risk4ExecutionProject manager: Eng. Sultan F. Al-Ghamdi · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦58%⁩ / ⁦67%⁩
SPI · CPI
0.87 · 0.96
Spend
SAR 52.2M / SAR 86.4M
Estimate at completion
SAR 90M

Schedule

⁦9%⁩ behind⁦58%⁩

Planned to date ⁦67%⁩

Forecast finish: 2027-05-126 Dhuʻl-Hijjah 1448 AH · 42 days late

SPI0.87Schedule performance index · 0.87CPI0.96Cost performance index · 0.96

Health dimensions

At risk

Last update: 2026-10-2716 Jumada I 1448 AH · Up to date

Deliverables

⁦2⁩ of ⁦8⁩ due deliverables accepted on time (⁦25%⁩)

Next milestones

  • Wave 1 development complete (24 services)2026-11-122 Jumada II 1448 AH
  • Nafath & Government Service Bus integration complete2026-12-101 Rajab 1448 AH
  • Penetration test passed, security sign-off2027-01-2820 Shaʻban 1448 AH
  • User acceptance testing complete2027-03-146 Shawwal 1448 AH

Top risks

  • Nafath and Government Service Bus integration interfaces not ready on time16
  • Shortage of integration and back-end engineers on the vendor team16
  • Late sign-off of membership-service requirements by the owning departments12
  • Possible critical findings in the pre-launch penetration test12

Open impediments

  • Shared Nafath test environment down for 9 days · Escalated
  • Vendor late delivering updated Government Service Bus interface specs · Open
  • Two vendor integration engineers withdrawn with no replacement · Overdue

Decisions and changes waiting

  • Review the returned data migration plan
  • Replacement plan for the vendor integration engineers
  • Access request: integration adviser on the Muqawil project
  • CR-2026-004 · Add membership transfer & record merge to the first release

Copilot summary

The project is 58% complete against 67% planned (SPI 0.87) and is forecast to finish on 12 May 2027 instead of 31 March 2027 — 42 days late. The slip sits in national-systems and agency integration (41% done) and the “Wave 1 complete” milestone, which missed 30 September and is now forecast for 12 November.

Three main causes: (1) the shared Nafath test environment was down for 9 days; (2) two vendor integration engineers left with no replacement — an impediment now overdue; (3) internal resource strain — the lead integration engineer is at 135% and shared with the mobile app. The membership-data migration plan was also returned for rework.

Saudi Contractors Authority · prepared by Eng. Sultan F. Al-Ghamdi in MunjazInternal

Status: At risk ·Project page