Muqawil Platform — Release 4
Remove from watchlistOne platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started