Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Electronic forms

The project’s twelve forms with their status and approval path, each printable with its approval log.

Forms

20

In approval

6

Past their limit

5

Escalated automatically

3

Approved

14

1SCA-PMO-F01Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

ApprovedV2 · ⁦2024-06-09⁩

2SCA-PMO-F02Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

ApprovedV4 · ⁦2024-08-03⁩

3SCA-PMO-F03Approval

Project weight

The weight and the relative weight in the portfolio

ApprovedV2 · ⁦2026-09-16⁩

4SCA-PMO-F04Initiation

Project charter

Objective, scope, deliverables, roles and budget

ApprovedV3 · ⁦2025-02-16⁩

5SCA-PMO-F05Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

ApprovedV3 · ⁦2025-01-30⁩

6SCA-PMO-F06Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

ApprovedV1 · ⁦2025-01-12⁩

10SCA-PMO-F10Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Not yet · Opens at the «Execution» stage

11SCA-PMO-F11Execution

Corrective plan

Actions, owners, dates and status

In approvalV2 · ⁦2026-10-25⁩
Technical acceptanceEng. Reem K. Al-DosariDue todayAction time limit about to lapse · Limit 3 working days

12SCA-PMO-F12Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Not yet · Opens at the «Closure» stage

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close