PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
SCA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-02-10⁩
Hijri
22 Shaʻban 1447 AH
ApprovedCR-2026-001Add a Nafath integration for company representatives and project owners

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Muqawil Platform — Release 4
Portfolio
Digital Services & Platforms Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Sultan F. Al-Ghamdi

1The change

TitleAuto-filled
Add a Nafath integration for company representatives and project owners
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Sultan F. Al-Ghamdi
Raised onAuto-filled
⁦2026-02-10⁩

Reason

The Services & Membership Sector asked for company representatives and project owners to submit membership and certificate requests on a delegation through Nafath

Justification

40% of requests are submitted by delegates of companies; without checking the delegation through Nafath they stay on paper

2Impact analysis

Cost

SAR +2.4M

Schedule

+18 days

Risk

12 → 16

Benefits

+18%

Risk impact

Adds more dependence on NIC interfaces

Benefits impact

Lifts e-submitted requests from 60% to 85%

3The approval decision

The PMO’s recommendation

The PMO recommends approval: the benefit clearly outweighs the cost

Change Committee decision
Approve
Decided on
⁦2026-02-23⁩
Decision number
DEC-2026-007

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4Submitted—⁦2026-02-10⁩ 10:19
2Project managerTechnical acceptanceEng. Sultan F. Al-GhamdiProject managerApproved—⁦2026-02-11⁩ 12:33
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-02-12⁩ 13:40
4Financial impactFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-02-15⁩ 11:38
5Contractual impactFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-02-17⁩ 12:15
6Change CommitteeTechnical acceptanceDr. Mohammed I. Al-SubaieChange CommitteeApproved—⁦2026-02-19⁩ 10:01

Signatures

Project manager

Eng. Sultan F. Al-Ghamdi

Approved⁦2026-02-11⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-02-12⁩

Financial impact

Munirah A. Al-Khalidi

Approved⁦2026-02-15⁩

Contractual impact

Mazen A. Al-Hazmi

Approved⁦2026-02-17⁩

Change Committee

Dr. Mohammed I. Al-Subaie

Approved⁦2026-02-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Sultan F. Al-Ghamdi on ⁦2026-02-10⁩

  1. Technical acceptance

    Project manager

    Eng. Sultan F. Al-Ghamdi · Project manager

    Approved · ⁦2026-02-11⁩ at ⁦12:33⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-02-12⁩ at ⁦13:40⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-02-15⁩ at ⁦11:38⁩

  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-02-17⁩ at ⁦12:15⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Approved · ⁦2026-02-19⁩ at ⁦10:01⁩

Steps that do not apply to this record

  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-02-23⁩

    Approved by the committee

    Eng. Sultan F. Al-Ghamdi

  2. V1Returned for edit⁦2026-02-10⁩

    The request as raised

    Eng. Sultan F. Al-Ghamdi