Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- SCA-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-02-10
- Hijri
- 22 Shaʻban 1447 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-014
- Project
- Muqawil Platform — Release 4
- Portfolio
- Digital Services & Platforms Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Eng. Majed S. Al-Rasheed
- Project manager
- Eng. Sultan F. Al-Ghamdi
1The change
- TitleAuto-filled
- Add a Nafath integration for company representatives and project owners
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Sultan F. Al-Ghamdi
- Raised onAuto-filled
- 2026-02-10
Reason
The Services & Membership Sector asked for company representatives and project owners to submit membership and certificate requests on a delegation through Nafath
Justification
40% of requests are submitted by delegates of companies; without checking the delegation through Nafath they stay on paper
2Impact analysis
Cost
SAR +2.4M
Schedule
+18 days
Risk
12 → 16
Benefits
+18%
Risk impact
Adds more dependence on NIC interfaces
Benefits impact
Lifts e-submitted requests from 60% to 85%
3The approval decision
The PMO’s recommendation
The PMO recommends approval: the benefit clearly outweighs the cost
- Change Committee decision
- Approve
- Decided on
- 2026-02-23
- Decision number
- DEC-2026-007
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4 | Submitted | — | 2026-02-10 10:19 |
| 2 | Project manager | Technical acceptance | Eng. Sultan F. Al-GhamdiProject manager | Approved | — | 2026-02-11 12:33 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-02-12 13:40 |
| 4 | Financial impact | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2026-02-15 11:38 |
| 5 | Contractual impact | Financial approval | Mazen A. Al-HazmiProcurement & contracts | Approved | — | 2026-02-17 12:15 |
| 6 | Change Committee | Technical acceptance | Dr. Mohammed I. Al-SubaieChange Committee | Approved | — | 2026-02-19 10:01 |
Signatures
Project manager
Eng. Sultan F. Al-Ghamdi
Approved2026-02-11
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-02-12
Financial impact
Munirah A. Al-Khalidi
Approved2026-02-15
Contractual impact
Mazen A. Al-Hazmi
Approved2026-02-17
Change Committee
Dr. Mohammed I. Al-Subaie
Approved2026-02-19