PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V3
Form date
⁦2025-01-30⁩
Hijri
30 Rajab 1446 AH
ApprovedPRJ-2026-014Muqawil Platform — Release 4

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Muqawil Platform — Release 4
Portfolio
Digital Services & Platforms Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Sultan F. Al-Ghamdi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-01-05⁩

Baseline finish

⁦2027-03-31⁩

Forecast finish

⁦2027-05-12⁩

SPI

0.87

MilestonePlannedForecastSlip
Charter approved⁦2025-01-05⁩⁦2025-01-05⁩0
Build & run contract signed⁦2025-04-30⁩⁦2025-05-04⁩+4 days
Advance payment (10%) released⁦2025-05-25⁩⁦2025-06-01⁩+7 days
Requirements & design signed off⁦2025-09-30⁩⁦2025-10-21⁩+21 days
Internal pilot (MVP) live⁦2026-03-31⁩⁦2026-04-28⁩+28 days
Data classification approved by the data office⁦2026-06-30⁩⁦2026-07-14⁩+14 days
Wave 1 development complete (24 services)⁦2026-09-30⁩⁦2026-11-12⁩+43 days
Nafath & Government Service Bus integration complete⁦2026-10-31⁩⁦2026-12-10⁩+40 days
Penetration test passed, security sign-off⁦2026-12-15⁩⁦2027-01-28⁩+44 days
User acceptance testing complete⁦2027-01-31⁩⁦2027-03-14⁩+42 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Business requirements document⁦10%⁩⁦2025-08-31⁩Lama S. Al-Harbi
UX prototype⁦6%⁩⁦2025-09-15⁩Maha F. Al-Khathami
Solution & integration design⁦6%⁩⁦2026-10-15⁩Eng. Asma S. Al-Hamdan
Wave 1 service package (24 services)⁦14%⁩⁦2026-09-30⁩Eng. Sultan F. Al-Ghamdi
Nafath integration interfaces⁦5%⁩⁦2026-10-31⁩Hussam T. Al-Qurashi
Government Service Bus integration interfaces⁦5%⁩⁦2026-11-15⁩Hussam T. Al-Qurashi
Data migration plan⁦3%⁩⁦2026-10-10⁩Rakan F. Al-Mohammadi
Master test plan⁦4%⁩⁦2026-06-30⁩Joud N. Al-Ahmadi
Performance & load test report⁦3%⁩⁦2026-12-20⁩Eng. Saad M. Al-Dosari
Change management & training plan⁦3%⁩⁦2026-10-31⁩Nouf M. Al-Balawi
User & operator guide⁦3%⁩⁦2027-02-15⁩Lama S. Al-Harbi
Internal pilot: the core platform and three services⁦30%⁩⁦2026-03-31⁩Eng. Sultan F. Al-Ghamdi
Approved service-data classification register⁦8%⁩⁦2026-06-30⁩Rakan F. Al-Mohammadi
Accepted with a certificate⁦58%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0001Nafath and Government Service Bus integration interfaces not ready on time16MitigateEng. Sultan F. Al-Ghamdi
RSK-0002Shortage of integration and back-end engineers on the vendor team16EscalateEng. Sultan F. Al-Ghamdi
RSK-0003Late sign-off of membership-service requirements by the owning departments12MitigateEng. Reem K. Al-Dosari
RSK-0006Possible critical findings in the pre-launch penetration test12MitigateEng. Yasser M. Al-Zahrani
RSK-0005Incomplete migration of membership and open-request data from legacy systems9MitigateRakan F. Al-Mohammadi
RSK-0007Membership and service-centre staff resisting the new digital procedures9MitigateNouf M. Al-Balawi
RSK-0009Reuse model-contracts components to shorten development9AcceptEng. Sultan F. Al-Ghamdi
RSK-0010Mobile-app team competing with the platform for the same people9MitigateEng. Reem K. Al-Dosari

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Steering CommitteeOverall status, variances, decisions neededMonthlyEng. Sultan F. Al-Ghamdi
Project sponsorThe periodic update card and top five risksWeeklyEng. Sultan F. Al-Ghamdi
Change Control BoardChange requests and impact analysisWeeklyEng. Sultan F. Al-Ghamdi
Service-owning departments and branchesPending requirements and sprint demosFortnightlyLama S. Al-Harbi
Digital Government AuthorityRelease plan and compliance test resultsAt each milestoneLama S. Al-Harbi
National Information Center (Nafath)Environment readiness and integration issuesWeeklyHussam T. Al-Qurashi
Membership and service-centre staffWhat changes in their work, training datesMonthlyNouf M. Al-Balawi
Member contractors and project ownersNew e-services and launch datesAt each milestoneNouf M. Al-Balawi
Team memberRoleAllocation
Eng. Sultan F. Al-GhamdiProject manager⁦100%⁩
Eng. Reem K. Al-DosariProgramme manager (oversight)⁦20%⁩
Eng. Majed S. Al-RasheedProject sponsor⁦20%⁩
Badr N. Al-HaqbaniProject owner⁦15%⁩
Hussam T. Al-QurashiLead integration engineer⁦100%⁩
Lama S. Al-HarbiSenior business analyst⁦80%⁩
Joud N. Al-AhmadiQA & test lead⁦70%⁩
Nouf M. Al-BalawiChange management specialist⁦30%⁩

5QualityAuto-filled

Quality leadAuto-filled
Joud N. Al-Ahmadi
Review cadenceAuto-filled
A code review each sprint; acceptance testing with each services wave
Next reviewAuto-filled
⁦2026-11-04⁩
Quality criterionThresholdNowMet
Automated test coverage70% or more per module58% (agency-integration module 48%)No
AccessibilityZero critical findings6 findings on the membership request formsNo
High-severity vulnerabilitiesZero before launchZero in the last scanYes
Page response timeUnder 2 s for 95% of requests1.4 sYes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Higher contractor satisfaction with digital services68 %88 %Faisal A. Al-Shehri
Lower cost per e-service transaction46 SAR / transaction18 SAR / transactionFaisal A. Al-Shehri
Shorter membership issue and renewal21 days5 daysEng. Reem K. Al-Dosari

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4Submitted—⁦2025-01-30⁩ 09:54
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-02-04⁩ 11:26
3Technical acceptance — project ownerTechnical acceptanceBadr N. Al-HaqbaniProject ownerApproved—⁦2025-02-05⁩ 12:33
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-02-09⁩ 10:49
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-02-10⁩ 11:26
6Sponsor approvalTechnical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2025-02-11⁩ 09:54

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-02-04⁩

Technical acceptance — project owner

Badr N. Al-Haqbani

Approved⁦2025-02-05⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-02-09⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2025-02-10⁩

Sponsor approval

Eng. Majed S. Al-Rasheed

Approved⁦2025-02-11⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V3

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Sultan F. Al-Ghamdi on ⁦2025-01-30⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-04⁩ at ⁦11:26⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Badr N. Al-Haqbani · Project owner

    Approved · ⁦2025-02-05⁩ at ⁦12:33⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-09⁩ at ⁦10:49⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-02-10⁩ at ⁦11:26⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2025-02-11⁩ at ⁦09:54⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V3ApprovedCurrent⁦2026-03-02⁩

    Updated after CR-2026-004; three services moved to wave 2

    • Schedule: wave 1 now 24 services instead of 27
    • Communications: a weekly report to the Steering Committee

    Eng. Sultan F. Al-Ghamdi

  2. V2Approved⁦2025-01-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Sultan F. Al-Ghamdi

  3. V1Returned for edit⁦2025-01-16⁩