Muqawil Platform — Release 4
Remove from watchlistOne platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Period
October 2026
- Progress
- 58%
- Planned
- 67%
- SPI
- 0.87
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-014-2026-10 | In approval | 58% | Methodology reviewDr. Noura M. Al-Otaibi5 working days overdueAction time limit exceeded · Limit 2 working days | 2026-10-26 |
| September 2026UPD-014-2026-09 | Approved | 55% | — | 2026-10-02 |
| August 2026UPD-014-2026-08 | Approved | 52% | — | 2026-09-02 |