Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

In approval5 working days overdueAction time limit exceeded · Limit 2 working daysEscalated
Progress
⁦58%⁩
Planned
⁦67%⁩
SPI
0.87
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-014-2026-10In approval⁦58%⁩Methodology reviewDr. Noura M. Al-Otaibi5 working days overdueAction time limit exceeded · Limit 2 working days⁦2026-10-26⁩
September 2026UPD-014-2026-09Approved⁦55%⁩—⁦2026-10-02⁩
August 2026UPD-014-2026-08Approved⁦52%⁩—⁦2026-09-02⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close