Original
Original baseline
- Finish
- 2027-03-13
- −18 days
- Budget
- SAR 84M
- 53 activities
Approved at the planning gate with the original SAR 84.0M budget and a March 2027 launch.
Approved 2025-02-16 · by Dr. Noura M. Al-Otaibi · via G3
One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved at the planning gate with the original SAR 84.0M budget and a March 2027 launch.
Approved 2025-02-16 · by Dr. Noura M. Al-Otaibi · via G3
Approved revised
CR-2026-001 added Nafath sign-in for company representatives and project owners: SAR 2.4M and 18 days on the critical path.
Approved 2026-02-24 · by Dr. Noura M. Al-Otaibi · via CR-2026-001
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Sultan F. Al-Ghamdi
What changed from version A to version B
Finish
2027-03-312027-05-12
+42 days
Budget
SAR 86.4MSAR 90.4M
+3.98 SAR M
Milestones moved
11 / 12
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference