Early warning: 74% chance of slipping within 45 days
Budget (BAC)
SAR 86.4M
Actual cost
SAR 52.2M
60% of budget
Progress
58%Awaiting acceptance 23%
Estimate at completion
SAR 90M
SAR +3.6M
SPI · CPI
0.87Schedule performance index · 0.870.96Cost performance index · 0.96
Forecast finish
2027-05-12
42 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure31 March 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Government Service Bus integrationPlanned: 2026-05-01 → 2026-10-31Forecast: 2026-05-20 → 2026-12-10Float: 0d
2027-01-3127%
SCA internal systems integrationPlanned: 2026-06-01 → 2026-12-31Forecast: 2026-06-15 → 2027-01-31Float: 101dDrag to change its duration+31
2026-12-100%
Nafath & Government Service Bus integration completePlanned: 2026-10-31 → 2026-10-31Forecast: 2026-12-10 → 2026-12-10Float: 0dDrag to change its datesNafath & Government Service Bus integration complete
2027-02-1045%
Data migrationPlanned: 2026-04-01 → 2026-12-31Forecast: 2026-04-01 → 2027-02-10Float: 91d
2026-11-3070%
Member & company data profiling & cleansingPlanned: 2026-04-01 → 2026-10-31Forecast: 2026-04-01 → 2026-11-30Float: 113dDrag to change its duration+30
2026-07-14100%
Data classification approved by the data officePlanned: 2026-06-30 → 2026-06-30Actual: 2026-07-14 → 2026-07-14Data classification approved by the data office
2027-02-1020%
Membership records migration & reconciliationPlanned: 2026-09-01 → 2026-12-31Forecast: 2026-09-20 → 2027-02-10Float: 91dDrag to change its duration+41