Muqawil Platform — Release 4
Remove from watchlistOne platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Team & roles
16 members, about 6.4 full-time equivalents
Leadership
4 members
- Eng. Sultan F. Al-GhamdiProject manager100%Allocated 115% across all projectsA
- Eng. Reem K. Al-DosariProgramme manager (oversight)20%C
- Eng. Majed S. Al-RasheedProject sponsor20%R
- Badr N. Al-HaqbaniProject owner15%R
Core team
4 members
- Hussam T. Al-QurashiLead integration engineer100%Allocated 135% across all projectsR
- Lama S. Al-HarbiSenior business analyst80%Allocated 120% across all projectsR
- Joud N. Al-AhmadiQA & test lead70%Allocated 110% across all projectsR
- Nouf M. Al-BalawiChange management specialist30%R
Specialists
5 members
- Eng. Asma S. Al-HamdanEnterprise architect30%C
- Rakan F. Al-MohammadiData engineer (migration)30%R
- Khalid N. Al-MutairiFinance & contracts officer20%I
- Eng. Yasser M. Al-ZahraniCybersecurity lead15%C
- Eng. Saad M. Al-DosariCloud & integration engineer15%R
Vendor team & advisers
3 members
- Maha F. Al-KhathamiFront-end developer40%R
- Karim HaddadDigital delivery adviser30%C
- Eng. Laila MansourArchitecture & integration adviser25%C
- Open seatIntegration engineer (vendor) — since 11 October
- Open seatIntegration engineer (vendor) — since 11 October
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
12 stakeholders, 8 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied3
high power, lower interest
Manage closely7
high power and interest
Monitor0
minimal effort
Keep informed2
high interest, lower power
Interest
Head of Digital Transformation — project sponsor
Eng. Majed Al-Rasheed
Sponsor — decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
At the level needed.
- Impact on the project
- Approves gates and major changes
- Engagement plan
- Monthly briefing, direct escalation within 48 h
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Majed Al-Rasheed | Head of Digital Transformation — project sponsor | Sponsor — decisions and funding | Leading | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa | 2026-10-21 | |||
| Dr. Abdullah Al-Qahtani | Secretary-General of the Authority | Steering Committee chair | SupportiveLeading | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesP-004r.aldosari@sca.sa | 2026-09-15 | |||
| Digital Government Authority | Regulator | Digital services regulator | NeutralSupportive | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Contractor ServicesP-006l.alharbi@sca.sa | 2026-10-27 | |||
| National Information Center (Nafath) | Integration partner | National identity provider | NeutralSupportive | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@sca.sa | 2026-10-26 | |||
| Badr Al-Haqbani | Membership & Contractor Services — project owner | Owner of the membership & contractor services | SupportiveLeading | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Contractor ServicesP-006l.alharbi@sca.sa | 2026-10-23 | |||
| National Cybersecurity Authority | Regulator | Cybersecurity regulator | NeutralSupportive | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | 2026-09-02 | |||
| Munirah Al-Khalidi | General Directorate of Finance & Procurement | Approves payments and certificates | Supportive | Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.sa | 2026-10-12 | |||
| Eng. Waleed Al-Juhani | Facilities O&M — owner of contractor service-centre readiness | Owner of contractor service-centre readiness | ResistantSupportive | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesP-004r.aldosari@sca.sa | 2026-10-08 | |||
| Member contractors and project owners | Beneficiaries | Member contractors and project owners | NeutralSupportive | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Contractor ServicesP-006l.alharbi@sca.sa | 2026-10-14 | |||
| Digital Platforms Solutions Co. | Main vendor | Main build & run vendor | Supportive | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa | 2026-10-26 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Steering CommitteeOverall status, variances, decisions neededMonthlyMeetingEng. Sultan F. Al-Ghamdi2026-11-17
- Project sponsorThe periodic update card and top five risksWeeklyReportEng. Sultan F. Al-Ghamdi2026-11-01
- Change Control BoardChange requests and impact analysisWeeklyMeetingEng. Sultan F. Al-Ghamdi2026-10-29
- Service-owning departments and branchesPending requirements and sprint demosFortnightlyWorkshopLama S. Al-Harbi2026-10-30
- Digital Government AuthorityRelease plan and compliance test resultsAt milestonesFormal letterLama S. Al-Harbi2026-11-12
- National Information Center (Nafath)Environment readiness and integration issuesWeeklyMeetingHussam T. Al-Qurashi2026-11-02Overdue
- Membership and service-centre staffWhat changes in their work, training datesMonthlyNewsletterNouf M. Al-Balawi2026-11-05
- Member contractors and project ownersNew e-services and launch datesAt milestonesSMSNouf M. Al-BalawiAt launch
- Main vendorActions due and performance against contractWeeklyMeetingEng. Sultan F. Al-Ghamdi2026-11-02
- Leadership and watchersPerformance and early warningsDailyDashboardDr. Noura M. Al-Otaibi2026-10-29
Coming up
By date
- 292026-10Change Control BoardMeeting · Weekly
- 292026-10Leadership and watchersDashboard · Daily
- 302026-10Service-owning departments and branchesWorkshop · Fortnightly
- 012026-11Project sponsorReport · Weekly
- 022026-11National Information Center (Nafath)Meeting · Weekly
- 022026-11Main vendorMeeting · Weekly