PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 86.4M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 3.6M
EAC SAR 90M
Revised request SAR 90.4M
  • Actual spendSAR 52.2M
  • Committed, not spentSAR 19.6M
  • Allotted, uncommittedSAR 12.5M
  • Contingency availableSAR 2.1M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 78.6M
Original budgetwhen the first baseline was approved
SAR 84M
Approved budgetafter approved change requests
SAR 86.4M
Current budgetavailable to spend now
SAR 86.4M
Revised budgetif the pending changes are approved
SAR 90.4M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 71.8M
Contracts3 active contracts
SAR 65.6M
Purchase orders⁦3⁩ orders
SAR 6.2M
Remaining budgetapproved less actual
SAR 34.2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 52.2M
Accrualswork done, not yet invoiced
SAR 2.4M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 90M
ContingencySAR 1.1M drawn of SAR 3.2M
SAR 2.1M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 78.6M
ApprovedSAR 86.4M
Estimate at completionSAR 90M
Approved is SAR 7.8M (⁦9.9%⁩) above the estimate
The estimate at completion is SAR 11.4M (⁦14.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-09-22⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61014
  • WBS elements⁦7⁩ elements · P-2026-014.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦28⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

Manual edit log
DateByFigureFrom → toReasonSource
⁦2026-10-05⁩10:20Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saActual spendSAR 51.8MSAR 52.2MSeptember cloud-hosting accruals posted before the finance system transferred themFinance department monthly reportFIN-RPT-2026-09
⁦2026-09-30⁩13:05Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.saEstimate at completionSAR 89.2MSAR 90MRe-estimated after the late first wave and a two-month extension of the integration teamProject manager’s estimate
⁦2026-08-12⁩09:40Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saCommitmentsSAR 69.4MSAR 71.8MSecurity scanning tools order added before the sync completedExport from the finance system (ERP)PO-2026-0812

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 1.1M drawn of SAR 3.2M

  • Nafath integration — extra test environment⁦2026-03-18⁩SAR 420K
  • Membership services — fee calculator linked to SADAD⁦2026-06-09⁩SAR 380K
  • Data migration — cleansing member-contractor records⁦2026-09-22⁩SAR 300K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Project management & governance6.746.034.926.99⁦−0.25⁩
2Requirements & contractor e-service design10.1210.3110.3110.31⁦−0.20⁩
3Core platform build25.2923.2620.1326.00⁦−0.71⁩
4National systems & agency integration15.1712.017.1116.29⁦−1.11⁩
5Data migration8.436.704.039.04⁦−0.61⁩
6Testing, quality & security10.127.744.0810.95⁦−0.83⁩
7Launch & change management8.435.751.619.37⁦−0.94⁩
Unallocated contingency2.100.000.001.05⁦+1.05⁩
Total86.4071.8052.2090.00⁦−3.60⁩

Budget split

WBS

SAR 86.4M

Budget

  • Project management & governanceSAR 6.7M⁦8%⁩
  • Requirements & contractor e-service designSAR 10.1M⁦12%⁩
  • Core platform buildSAR 25.3M⁦29%⁩
  • National systems & agency integrationSAR 15.2M⁦18%⁩
  • Data migrationSAR 8.4M⁦10%⁩
  • Testing, quality & securitySAR 10.1M⁦12%⁩
  • Launch & change managementSAR 8.4M⁦10%⁩
  • Unallocated contingencySAR 2.1M⁦2%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-06-27⁩+88

SPI(t) ⁦0.90⁩ against the approved finish ⁦2027-03-31⁩

Planned valuePV
SAR 57.9M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 50.1M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 52.2M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 86.4M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−2.09⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−7.78⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.96
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.87
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 90M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 37.8M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−3.60⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.06
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 90M
  • If the rest goes to planSAR 88.5M
  • At cost and schedule performanceSAR 95.9M
  • The PM’s bottom-up estimateSAR 90M
  • To stay within SAR 86.4M, cost performance on the rest must rise to ⁦1.06⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 90M

Variance at completion: ⁦−3.60⁩ SAR M