PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-01-12⁩
Hijri
12 Rajab 1446 AH
ApprovedMTG-KO-014Kick-off — Muqawil Platform — Release 4

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Muqawil Platform — Release 4
Portfolio
Digital Services & Platforms Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Sultan F. Al-Ghamdi

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Muqawil Platform — Release 4
Date and timeAuto-filled
⁦2025-01-12⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Eng. Sultan F. Al-Ghamdi

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Majed S. Al-RasheedHead, Digital Transformation Sector
Badr N. Al-HaqbaniDirector General, Membership & Contractor Services
Eng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Eng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-Services
Eng. Majed S. Al-RasheedHead, Digital Transformation Sector
Badr N. Al-HaqbaniDirector General, Membership & Contractor Services

2Roles

PersonRoleDuty
Eng. Majed S. Al-RasheedProject sponsorSponsors the project, decides escalations and material changes
Badr N. Al-HaqbaniProject ownerApproves the requirements and accepts the deliverables
Eng. Sultan F. Al-GhamdiProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Reem K. Al-DosariProgramme manager (oversight)Delivers their tasks and uploads the evidence
Eng. Majed S. Al-RasheedProject sponsorDelivers their tasks and uploads the evidence
Badr N. Al-HaqbaniProject ownerDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Charter approvedEng. Majed S. Al-Rasheed⁦2025-01-05⁩Done
Build & run contract signedKhalid N. Al-Mutairi⁦2025-04-30⁩Done
Advance payment (10%) releasedKhalid N. Al-Mutairi⁦2025-05-25⁩Done
Requirements & design signed offLama S. Al-Harbi⁦2025-09-30⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Projects Steering Committee: Strategic decisions, escalations, major gates (Monthly)
  3. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-05-15⁩
Start confirmed
Eng. Majed S. Al-Rasheed · ⁦2025-01-13⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4Submitted—⁦2025-01-13⁩ 10:19
2Chair’s approval (sponsor)Technical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2025-01-14⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-01-15⁩ 14:53

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-01-15⁩

Chair’s approval (sponsor)

Eng. Majed S. Al-Rasheed

Approved⁦2025-01-14⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Sultan F. Al-Ghamdi on ⁦2025-01-13⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-01-15⁩ at ⁦14:53⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2025-01-14⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-01-12⁩

    The minutes as taken

    Eng. Sultan F. Al-Ghamdi

Only one version so far.