Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- SCA-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-10-15
- Hijri
- 4 Jumada I 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-014
- Project
- Muqawil Platform — Release 4
- Portfolio
- Digital Services & Platforms Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Eng. Majed S. Al-Rasheed
- Project manager
- Eng. Sultan F. Al-Ghamdi
1The change
- TitleAuto-filled
- Add membership transfer & record merge to the first release
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Reem K. Al-Dosari
- Raised onAuto-filled
- 2026-10-15
Reason
The membership & contractor services directorate asked to bring membership transfer and record merge into the first release
Justification
About 3,200 transfer and merge requests come in a month; leaving the service for wave 2 keeps them on paper six more months and loads the contractor service centres
2Impact analysis
Cost
SAR +1.9M
Schedule
+21 days
Risk
12 → 15
Benefits
+7%
Risk impact
Adds requirements the membership department and the branches must sign, and loads the integration team
Benefits impact
3,200 transfer and merge requests a month digitised six months early
3The approval decision
The PMO’s recommendation
The PMO recommends conditional approval: add the service once the Government Service Bus integration is done, and win back part of the days through CR-2026-012
- Change Committee decision
- Not taken yet
- Decided on
- —
- Decision number
- —
Conditions
- The service does not start before the Government Service Bus integration is complete
- Approve CR-2026-012 to add integration capacity
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-Services | Submitted | — | 2026-10-15 13:40 |
| 2 | Project manager | Technical acceptance | Eng. Sultan F. Al-GhamdiProject manager | Approved | — | 2026-10-18 09:24 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-10-20 10:31 |
| 4 | Financial impact | Financial approval | Approval engineFinance | Pre-breach alert | — | 2026-10-22 08:00 |
Signatures
Project manager
Eng. Sultan F. Al-Ghamdi
Approved2026-10-18
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-10-20
Financial impact
Munirah A. Al-Khalidi
Awaiting decision
Contractual impact
Mazen A. Al-Hazmi
Later
Change Committee
Dr. Mohammed I. Al-Subaie
Later