PRJ-2026-014At risk4ExecutionHybrid

Muqawil Platform — Release 4

Remove from watchlist

One platform for 68 e-services for contractors — membership and renewal, certificates, qualification programmes, model contracts — with Nafath sign-in and links to the commercial register, Balady and Etimad through the Government Service Bus.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-06-09⁩
Hijri
3 Dhuʻl-Hijjah 1445 AH
ApprovedDMD-2026-014Muqawil Platform — Release 4

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Muqawil Platform — Release 4
Portfolio
Digital Services & Platforms Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Sultan F. Al-Ghamdi

1The proposalAuto-filled

TitleAuto-filled
Muqawil Platform — Release 4
Proposed byAuto-filled
Eng. Sultan F. Al-Ghamdi
DepartmentAuto-filled
Muqawil Platform & e-Services Department
Submitted onAuto-filled
⁦2024-06-09⁩
Proposal numberAuto-filled
DMD-2026-014

2Justification

The Authority runs 68 e-services for contractors through five separate channels and legacy systems that do not talk to each other; a contractor deals with several departments and service centres for a single request, and issuing or renewing a membership takes 21 days on average. Release 4 of the Muqawil platform brings them into one digital journey that meets Digital Government Authority standards.

3Objectives

  1. Bring 68 contractor e-services into Muqawil with a single journey
  2. Cut the average time to issue or renew a membership from 21 days to 5
  3. Lift contractor satisfaction with digital services to 88%
  4. Reduce cost per transaction by 60%

Strategic objectives served

  • SO-1.1 — Simplify regulatory relationships and make doing business easier
  • SO-1.2 — Raise quality standards across contracting
  • SO-2.3 — Transparency and open sector information

4Expected benefits

KindBenefit
SatisfactionHigher contractor satisfaction with digital services — target 88 %
Cost savingLower cost per e-service transaction — target 18 SAR / transaction
Time savedShorter membership issue and renewal — target 5 days

5Cost & feasibility

Estimated cost

SAR 86.4M

Funding

Digital Transformation Sector capital budget 2025–2027, line 2-3-114

Cost lineAmount
Build & run contract (incl. approved variation)SAR 51M
Cloud hostingSAR 9.2M
Identity & integration licencesSAR 7.2M
SCA internal teamSAR 6.1M
QA & project office supportSAR 5.4M
Change management & trainingSAR 3.1M
Contingency reserve (5%)SAR 4.4M
TotalSAR 86.4M

6Initial risks

RiskLevelProposed response
Nafath and Government Service Bus interfaces lateHighTreated in the risk management plan
Vendor integration engineers in short supplyHighTreated in the risk management plan
Late requirement sign-off by the service-owning departmentsMediumTreated in the risk management plan
Membership and service-centre staff resisting the digital proceduresMediumTreated in the risk management plan
Critical penetration-test findingsMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4Submitted—⁦2024-06-09⁩ 13:22
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-06-10⁩ 11:02
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-06-11⁩ 12:09
4Portfolio manager reviewTechnical acceptanceFaisal A. Al-ShehriPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-06-13⁩ 13:16
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-06-18⁩ 13:58
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-06-19⁩ 09:30

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-06-10⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-06-11⁩

Portfolio manager review

Faisal A. Al-Shehri

Approved⁦2024-06-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-06-18⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-06-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Sultan F. Al-Ghamdi on ⁦2024-06-09⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-06-10⁩ at ⁦11:02⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-06-11⁩ at ⁦12:09⁩

  3. Technical acceptance

    Portfolio manager review

    Faisal A. Al-Shehri · Portfolio manager

    Approved · ⁦2024-06-13⁩ at ⁦13:16⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-06-18⁩ at ⁦13:58⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-06-19⁩ at ⁦09:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-06-30⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Sultan F. Al-Ghamdi

  2. V1Returned for edit⁦2024-06-09⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal