RSK-0021 Material
Main contractor cash-flow distress and unpaid subcontractors
Al-Khobar Branch — Rehabilitation & Extension Financial 25 Critical SAR 36M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@sca.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 1 d RSK-0015 Material
Steel and concrete price rises driving price-adjustment claims
SCA Headquarters, Riyadh Financial 20 Critical SAR 48M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects P-020 · a.asiri@sca.sa Escalate Escalated In 18 days 2026-11-15 · 5 Jumada II 1448 AH 4 d RSK-0016 Material
Late handover of the northern plot and utility diversions in zones 3 and 4
SCA Headquarters, Riyadh Schedule 20 Critical SAR 31M Eng. Bandar M. Al-Shammari Eng. Bandar M. Al-Shammari Director General, Facilities & Premises P-013 · b.alshammari@sca.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0026 Material
Contractor financial claims piling up over unapproved variations
SCA Academy Campus, Riyadh Financial 20 Critical SAR 41M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Academy Facilities P-022 · s.almalki@sca.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 3 d RSK-0034 Material
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16
Qassim Vocational Qualification Centre Technical 20 Critical SAR 27M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects P-020 · a.asiri@sca.sa Escalate Escalated In 23 days 2026-11-20 · 10 Jumada II 1448 AH 5 d RSK-0044 Material
Late land handover and title deed from the owning entity in Wadi Al-Dawasir
Wadi Al-Dawasir Vocational Qualification Centre Regulatory 20 Critical SAR 12M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Academy Facilities P-022 · s.almalki@sca.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 22 d RSK-0001 Material
Nafath and Government Service Bus integration interfaces not ready on time
Muqawil Platform — Release 4 Technical 16 High SAR 2.4M Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, Muqawil Platform — Release 4 P-005 · s.alghamdi@sca.sa Mitigate Open In 18 days 2026-11-15 · 5 Jumada II 1448 AH 2 d RSK-0002 Material
Shortage of integration and back-end engineers on the vendor team
Muqawil Platform — Release 4 Resource 16 High SAR 1.9M Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, Muqawil Platform — Release 4 P-005 · s.alghamdi@sca.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 2 d RSK-0012 Material
Customisation and Etimad integration costs exceeding the approved contingency
SCA ERP System Financial 16 High SAR 6.8M Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Systems & Integration P-025 · d.alsaleh@sca.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 5 d RSK-0017 Material
Contractor claim for a 120-day extension with compensation
SCA Headquarters, Riyadh Contractual 16 High SAR 18.5M Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Procurement Specialist P-007 · k.almutairi@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 8 d RSK-0019 Material
Exchange-rate swings on imported equipment without fixed prices
SCA Backup Data Centre Financial 16 High SAR 7.4M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@sca.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 7 d RSK-0024 Material
Ground-improvement costs up after the geotechnical survey
Jeddah Branch & Qualification Centre Financial 16 High SAR 22.5M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Regional Qualification Centres P-023 · f.alsulami@sca.sa Escalate Escalated In 15 days 2026-11-12 · 2 Jumada II 1448 AH 6 d RSK-0027 Material
Late delivery of curtain-wall glazing from the overseas factory
SCA Academy Campus, Riyadh Schedule 16 High SAR 15M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Academy Facilities P-022 · s.almalki@sca.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 3 d RSK-0036 Material
Municipality late bringing utilities and access roads to the site
Arar Vocational Qualification Centre Financial 16 High SAR 14M Yousef A. Al-Omari Yousef A. Al-Omari Director General, Partnerships & Events P-016 · y.alomari@sca.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 56 d RSK-0043 Material
Funding left out of the 2027 budget, keeping the tender suspended
Energy Retrofit of Existing SCA Buildings (ESCO) Financial 16 High SAR 4.8M Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Energy Efficiency P-028 · m.alotaibi@sca.sa Escalate Escalated In 48 days 2026-12-15 · 6 Rajab 1448 AH 20 d RSK-0022 Material
Fire-fighting and evacuation systems failing Civil Defence requirements
Al-Khobar Branch — Rehabilitation & Extension Regulatory 15 High SAR 12M Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Energy Efficiency P-028 · m.alotaibi@sca.sa Mitigate Open In 79 days 2027-01-15 · 7 Shaʻban 1448 AH 9 d RSK-0028 Material
Possible removal of the MEP subcontractor
SCA Academy Campus, Riyadh Contractual 15 High SAR 9.5M Eng. Abdulrahman S. Al-Harbi Eng. Abdulrahman S. Al-Harbi Dean, SCA Academy P-014 · ab.alharbi@sca.sa Mitigate Open In 28 days 2026-11-25 · 15 Jumada II 1448 AH 10 d RSK-0046 Material
Tender prices 18% above the engineer’s estimate
Asir Vocational Qualification Centre Financial 15 High SAR 93.6M Eng. Ibrahim A. Al-Ghamdi Eng. Ibrahim A. Al-Ghamdi Director, Engineering Supervision P-036 · i.alghamdi@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0003
Late sign-off of membership-service requirements by the owning departments
Muqawil Platform — Release 4 Stakeholder 12 Medium SAR 1.2M Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Head of the Muqawil Platform & Programme Manager, Muqawil & e-Services P-004 · r.aldosari@sca.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 6 d RSK-0006
Possible critical findings in the pre-launch penetration test
Muqawil Platform — Release 4 Security 12 Medium SAR 600K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@sca.sa Mitigate Open In 74 days 2027-01-10 · 2 Shaʻban 1448 AH 8 d RSK-0013
Late migration and reconciliation of historical financial data
SCA ERP System Schedule 12 Medium SAR 2.1M Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Systems & Integration P-025 · d.alsaleh@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0020
Late delivery of cooling units and standby generators
SCA Backup Data Centre Schedule 12 Medium SAR 3.2M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 7 d RSK-0023
Central HVAC failures during commissioning
Al-Khobar Branch — Rehabilitation & Extension Technical 12 Medium SAR 5.6M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@sca.sa Mitigate Open In 53 days 2026-12-20 · 11 Rajab 1448 AH 9 d RSK-0025
Late building permits from the Jeddah municipality
Jeddah Branch & Qualification Centre Regulatory 12 Medium SAR 6M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Regional Qualification Centres P-023 · f.alsulami@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 6 d RSK-0031
Late integration of the central monitoring room with building systems
Smart Test-hall Proctoring & Access Control Technical 12 Medium SAR 1.4M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0033
Municipal objections to trenching in built-up districts
Secure Enterprise Network Stakeholder 12 Medium SAR 2.2M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 37 d RSK-0035
Pile lengths exceeding contract quantities
Qassim Vocational Qualification Centre Cost 12 Medium SAR 8.4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects P-020 · a.asiri@sca.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 5 d RSK-0018
Safety incidents around cranes and deep excavations
SCA Headquarters, Riyadh Technical 10 Medium SAR 4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects P-020 · a.asiri@sca.sa Mitigate In progress In 245 days 2027-06-30 · 25 Muharram 1449 AH 14 d RSK-0042
Undetected vulnerabilities in legacy systems before SOC onboarding
SCA Cybersecurity Programme Security 10 Medium SAR 3M Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@sca.sa Mitigate In progress In 34 days 2026-12-01 · 21 Jumada II 1448 AH 2 d RSK-0005
Incomplete migration of membership and open-request data from legacy systems
Muqawil Platform — Release 4 Technical 9 Medium SAR 750K Rakan F. Al-Mohammadi Rakan F. Al-Mohammadi Data Engineer P-032 · r.almohammadi@sca.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 7 d RSK-0007
Membership and service-centre staff resisting the new digital procedures
Muqawil Platform — Release 4 Stakeholder 9 Medium SAR 300K Nouf M. Al-Balawi Nouf M. Al-Balawi Change Management Specialist P-035 · n.albalawi@sca.sa Mitigate In progress In 110 days 2027-02-15 · 8 Ramadan 1448 AH 13 d RSK-0010
Mobile-app team competing with the platform for the same people
Muqawil Platform — Release 4 Resource 9 Medium SAR 520K Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Head of the Muqawil Platform & Programme Manager, Muqawil & e-Services P-004 · r.aldosari@sca.sa Mitigate Open In 21 days 2026-11-18 · 8 Jumada II 1448 AH 3 d RSK-0048
Cloud hosting contract signed late
Muqawil Platform — Release 4 Contractual 9 Medium — Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Procurement Specialist P-007 · k.almutairi@sca.sa Accept Closed 2025-07-01 2025-07-01 · 6 Muharram 1447 AH 479 d RSK-0014
Implementation consultants’ contracts ending before go-live
SCA ERP System Resource 9 Medium SAR 900K Munirah A. Al-Khalidi Munirah A. Al-Khalidi Director General, Finance & Procurement P-018 · m.alkhalidi@sca.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 12 d RSK-0029
Cloud consumption costs above estimate
SCA Systems Migration to the Cloud Financial 9 Medium SAR 2.6M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@sca.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 11 d RSK-0030
Camera and gate quantity variances between drawings and site
Smart Test-hall Proctoring & Access Control Financial 9 Medium SAR 1.8M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0032
Higher reinstatement costs after network trenching
Secure Enterprise Network Financial 9 Medium SAR 3.9M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@sca.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 37 d RSK-0037
Too few accredited data owners in the sectors and departments
Contracting Sector Information Centre & Data Governance Resource 9 Medium SAR 650K Rahaf I. Al-Nefaie Rahaf I. Al-Nefaie Director, Data & Innovation P-027 · r.alnefaie@sca.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 8 d RSK-0038
High UAT defect count in the outgoing-mail module
Correspondence & Document Management System (DMS) Technical 9 Medium SAR 480K Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Systems & Integration P-025 · d.alsaleh@sca.sa Mitigate Open In 13 days 2026-11-10 · 30 Jumada I 1448 AH 7 d RSK-0039
Late supply of training-hall audio-visual systems
Hail Vocational Qualification Centre Schedule 9 Medium SAR 2.1M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Regional Qualification Centres P-023 · f.alsulami@sca.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0040
Low uptake of the Irtiqaa self-assessment among small contractors
Irtiqaa Portal — Release 2 Stakeholder 9 Medium SAR 250K Ghada A. Al-Shahrani Ghada A. Al-Shahrani Director, Qualification Programmes & Capability P-029 · g.alshahrani@sca.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 34 d RSK-0047
Privacy requirements for e-test recordings under the Personal Data Protection Law
Electronic Skills-test Halls — Makkah Region Regulatory 9 Medium SAR 900K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@sca.sa Mitigate Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 10 d RSK-0004
Cloud hosting capacity exceeded at launch
Muqawil Platform — Release 4 Technical 8 Medium SAR 900K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@sca.sa Mitigate In progress In 48 days 2026-12-15 · 6 Rajab 1448 AH 9 d RSK-0008
Late delivery of identity & access management licences
Muqawil Platform — Release 4 Contractual 6 Low SAR 450K Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Procurement Specialist P-007 · k.almutairi@sca.sa Transfer Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 10 d RSK-0011
Updated user-experience standards from the Digital Government Authority
Muqawil Platform — Release 4 Regulatory 6 Low SAR 280K Lama S. Al-Harbi Lama S. Al-Harbi Senior Business Analyst — Contractor Services P-006 · l.alharbi@sca.sa Accept Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 16 d RSK-0045
Preliminary-handover snags on the fire and alarm systems
Khamis Mushait Training Centre Rehabilitation Technical 6 Low SAR 600K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@sca.sa Mitigate Open In 15 days 2026-11-12 · 2 Jumada II 1448 AH 2 d